HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Units
90 units
Mix
50 × 1 BHK · 32 × Multipurpose · 8 × Mutipurpose Room
Carpet area
24–30 sq mper-unit range, as filed
Floors
5
Buildings
2
Land area
2,425 sq m
Sanctioned built-up
3,150 sq m

Timeline

RERA registeredJun 2019
Proposed completionAug 2024
TodayJul 2026
Construction progress
Podiums0%
Storm Water Drains0%
Water conservation…0%
Electrical meter r…0%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

90 units across 4 batches
TypeArea sq mCount
Mutipurpose Room248
Multipurpose2532
1 BHK2910
1 BHK3040

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Promoter registration

Abhijeet Chandrakant Bhansali

IndividualPromoter type
Thane, MAHARASHTRABased in
2Projects
1City
2019–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
170 homeson the public record across 2 projects
6,076 sq mbuilt-up filed
4,628 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Pashane
Taluka
Karjat
District
Raigarh
Pincode
410201
Survey no.
Plot No. 136/1/12
North boundary
Survey no 152
East boundary
Road
South boundary
plot no 13 and14
West boundary
survey no 152
What’s nearby
SchoolsNo schools within 2km
HealthcareNo hospital within 5km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Primary road 1.7 km · Karjat RoadRailway line 1.6 kmRailway station 1.8km away (Vangani)Limited bus connectivity nearby
Water & environment
Water body 557 mRiver 868 m · Ulhas
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Collector Raigad Alibaug

Collector office
Building Permit
Survey no. Plot No. 136/1/12

The promised possession date (23 Aug 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.