Complete project overview

MahaRERA · Registration filing
Floors
12
Buildings
2
Parking
2 spaces
Land area
2,655 sq m
Sanctioned built-up
15,269 sq m

Timeline

RERA registeredAug 2017
Proposed completionOct 2020
TodayJul 2026
Construction progress
Storm Water Drains0%
Energy managemcnt0%
Landscaping & Tree…90%
Street Lighting90%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Sewerage (Chamber,…100%
Solid Waste Manage…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

WESTERN REAL ESTATE PVT. LTD.

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Mira-Bhayandar (M Corp.)
Taluka
Thane
District
Thane
Pincode
401107
Survey no.
154
North boundary
SURVEY NO 155
East boundary
30MTRS WIDE DP ROAD
South boundary
SURVEY NO 22-23
West boundary
SURVEY NO 16-17
What’s nearby
Schools2 schools within 500m · 7 educational institutions within 1km
HealthcareHospital 44m away · 7 clinics within 1km · Pharmacy within 1km
LifestylePark 947m away · Gym or sports centre 1.1km away · 14+ restaurants and cafes within 1km
ShoppingSupermarket 635m away · Bank 54m away
Getting around
Expressway 3.1 km · Western Express HighwayPrimary road 60 m · Mira Bhayandar RoadRailway line 781 mRailway station 1.3km away (Mira Road)Bus stop within 500m
Water & environment
Water body 560 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Mira Bhayander Mahanagar Corporation

Building Permit
Survey no. 154

The promised possession date (30 Oct 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation2 cases on record, earliest 2014
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.