HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Plots
77 plots
Land area
22,200 sq m
Sanctioned built-up
14,160 sq m

Timeline

RERA registeredSep 2017
Proposed completionMar 2022
TodayJul 2026
Construction progress
Storm Water Drains0%
Landscaping & Tree…10%
Street Lighting20%
Treatment And Disp…20%
Internal Roads & F…50%
Water Supply50%
Sewerage (Chamber,…50%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

VIVID BUILDCOM

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2017–2022Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kawathe
Taluka
Wai
District
Satara
Pincode
415516
Survey no.
GAT NO 915-B
North boundary
GAT NO 1029
East boundary
VILLAGE ROAD
South boundary
GAT NO 914
West boundary
GAT NO 915
What’s nearby
Schools1 school within 500m · 10 educational institutions within 1km · College or university 1.4km away
HealthcareHospital 159m away · 19 clinics within 1km · Pharmacy within 500m
LifestylePark 664m away · Gym or sports centre 442m away · 56+ restaurants and cafes within 1km
ShoppingSupermarket 454m away · Mall 300m away · Bank 102m away
Getting around
Expressway 2.3 km · Bajirao RoadPrimary road 223 m · Karve RoadRailway line 3.4 kmMetro station 367m away (SNDT College)6 bus stops within 500m
Water & environment
Water body 375 mRiver 464 m · Mutha
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Assistance Director Of Town Plannig Branch Satara

Layout Permit
Survey no. GAT NO 915-B

The promised possession date (30 Mar 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
Appeals1 appeal before the tribunal
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

1 complaint on MahaRERA’s register for this project 1 disposed.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.