RERA Bihar · Registration filing
Units
224 units
Unit mix
118 × 3 BHK · 104 × 2 BHK · 2 × Shop
Buildings
5
Parking
230 spaces
Land area
7,516 sq m
Built-up area
18,788 sq m

Timeline

Project startedJan 2016
RERA registeredMay 2018
Proposed completionDec 2022
TodayJul 2026

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

224 units across 9 batches
BuildingTypeArea sq mCount
WINSOME EMPIRE BLOCK "C"3 BHK014
WINSOME EMPIRE BLOCK "D"3 BHK028
WINSOME EMPIRE BLOCK"A"3 BHK038
WINSOME EMPIRE BLOCK"A"2 BHK056
WINSOME EMPIRE BLOCK"B"3 BHK024
WINSOME EMPIRE BLOCK"B"2 BHK048
WINSOME EMPIRE BLOCK"C"3 BHK014
WINSOME EMPIRE BLOCK"C"Shop1041
WINSOME EMPIRE BLOCK"C"Shop1001

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RERA Bihar · Promoter registration

WINSOME INFRASTRUCTURE

Partnership FirmPromoter type
Patna, BiharBased in
---Select---Also RERA-registered in
4Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
447 homeson the public record across 4 projects
66,971 sq mbuilt-up filed
14,114 sq mland declared
₹104.22 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Bihar · Registration filing
District
Patna
City / town
PATNA
Anchal (block)
Danapur
Mauja (revenue village)
Sikandarpur
Village
GHUDAUD ROAD
Address
BISCUIT FACTORY ROAD, NASRIGANJ, DANAPUR, PATNA BIHAR
What’s nearby
Schools1 school within 1km · College or university 950m away · Library 1.1km away
HealthcareHospital 1.7km away · 2 clinics within 1km
LifestylePark 1.9km away · Gym or sports centre 963m away
ShoppingSupermarket 1.4km away
Getting around
Expressway 2.7 kmPrimary road 926 mRailway line 897 mRailway station 1.5km away (Digha Bridge Halt)Limited bus connectivity nearby
Water & environment
River 1.5 km · GangesCanal 1.8 km · Barun Canal
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹38.68 Cr declared to build 224 flats. What that works out to:

₹17.27 Lakhdeclared cost per flatall-in — land + construction
₹1,913/sq ftof built-up area₹20,587/sq m
22%of the cost is land₹1,073/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RERA Bihar · Approved building plan
Building Permit

The promised possession date (31 Dec 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Bihar does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Bihar does not publish a complaints register. This read cannot speak to them either way.