HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
12
Buildings
4
Parking
90 spaces
Land area
9,266 sq m
Sanctioned built-up
17,190 sq m

Timeline

RERA registeredApr 2022
Proposed completionMay 2026
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
Open Parking0%
Internal Roads & F…57%
Stairs & lifts60%
Internal finishes62%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Superb Maa Infra and Housing LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
2Projects
1City
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2 projectson the public record across 2 projects
58,158 sq mbuilt-up filed
41,096 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Maharashtra State Road Development Corporationthis project1 of 2 projects
Maharashtra State Road Development Corporation Limited1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Giravale
Taluka
Panvel
District
Raigarh
Pincode
410221
Survey no.
24/2/a and 24/2/b
North boundary
S No 42
East boundary
Road to Giravale Village
South boundary
S No 24 pt 3 and D P Road
West boundary
S No 40 and 41
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 992 mPrimary road 987 mRailway line 781 m · Vasai Road-Roha LineRailway station 1.1km away (Somatne)Limited bus connectivity nearby
Water & environment
River 856 mWater body 1.6 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra State Road Development Corporation

Building Permit
Survey no. 24/2/a and 24/2/b

The promised possession date (31 May 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Maharashtra State Road Development Corporation

Planning authority

Has approved 32 RERA projects0.2% of Maharashtra.

an apartments market75% apartments · 25% plotted layouts. Apartments like yours are this body's core business.

Builders
22
On record
161 flats · 1,218 plots
Reach
3 districts
Since
2017

More layout-heavy than Maharashtra overall — 25% plots here vs 5% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.