HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
74 spaces
Land area
1,582 sq m
Sanctioned built-up
4,693 sq m

Timeline

RERA registeredFeb 2025
Proposed completionDec 2028
TodayJul 2026
Construction progress
Podiums0%
Stilt floor0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Internal finishes50%
Stairs & lifts60%
Plinth95%
Excavation98%
Basement (if any)98%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

MPR Builders and Developers LLP

PartnershipPromoter type
Mumbai City, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Greater Mumbai (M Corp.) (Part) (802794)
Taluka
Mumbai
District
Mumbai Suburban
Pincode
400057
Survey no.
FP No.54 ,T.P. Scheme- TPS Vile Parle No.II
North boundary
Prarthana Samaj Road
East boundary
Final Plot No 53
South boundary
Plot No 107
West boundary
Final Plot No 55 Part and Final Plot No 56 Part
What’s nearby
Schools3 schools within 500m · 7 educational institutions within 1km · Library 198m away
HealthcareHospital 51m away · 8 clinics within 1km · Pharmacy within 500m
LifestylePark 1.6km away · Gym or sports centre 508m away · 28+ restaurants and cafes within 1km
ShoppingSupermarket 427m away · Convenience store within 500m · Bank 225m away
Getting around
Expressway 1.8 kmPrimary road 523 m · Service roadRailway line 525 m · Western Railway (Fast)Railway station 584m away (Vile Parle)15 bus stops within 500m
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. FP No.54 ,T.P. Scheme- TPS Vile Parle No.II
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation4 cases on record, earliest 2022
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.