Complete project overview

MahaRERA · Registration filing
Floors
11
Buildings
2
Parking
40 spaces
Land area
996 sq m
Sanctioned built-up
2,688 sq m

Timeline

RERA registeredAug 2017
Proposed completionDec 2019
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Internal Roads & F…100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Landscaping & Tree…100%
Street Lighting100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

ZEE INFRA PROJECTS PRIVATE LIMITED

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
5Projects
1City
2017–2023Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
102 homeson the public record across 5 projects
10,687 sq mbuilt-up filed
4,969 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Bmcthis project1 of 2 projects
Municipal Corporation of Greater MumbaiMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Andheri
Taluka
Andheri
District
Mumbai Suburban
Pincode
400056
Survey no.
838,838 1 TO 4
North boundary
OTHER PORTION NO 3
East boundary
RAILWAY
South boundary
PLOT NO 55
West boundary
SURVEY NO 236
What’s nearby
Schools1 school within 500m · 8 educational institutions within 1km · Library 688m away
HealthcareHospital 313m away · 19 clinics within 1km · Pharmacy within 500m
LifestylePark 1.8km away · Gym or sports centre 988m away · 43+ restaurants and cafes within 1km
ShoppingSupermarket 775m away · Convenience store within 500m · Bank 440m away
Getting around
Expressway 1.8 km · Andheri FlyoverPrimary road 457 m · Swami Vivekanand RoadRailway line 250 mRailway station 724m away (Vile Parle)8 bus stops within 500m
Water & environment
Water body 206 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Bmc

Building Permit
Survey no. 838,838 1 TO 4

The promised possession date (31 Dec 2019) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Bmc

Planning authority

Has approved 46 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
46
On record
1,091 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.