HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Plots
120 plots
Land area
40,560 sq m
Recreational open space
4,042 sq m

Timeline

RERA registeredAug 2024
Proposed completionMar 2027
TodayJul 2026
Construction progress
Street Lighting0%
Community Building…0%
Aggregate area of …0%
Water Supply10%
Landscaping & Tree…10%
Internal Roads & F…25%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Elite Promoters and Builders

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Urse
Taluka
Mawal
District
Pune
Pincode
410506
Survey no.
Gat No. 226, 244, 245 & 246
North boundary
By Gat No 240 and 248
East boundary
By Gat No 242 and 243
South boundary
By Gat No 227 and 228
West boundary
By Gat No 225
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.7km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.5 km · Urse Talegaon RoadPrimary road 1.0 km · Urse Talegaon RoadRailway line 4.1 km · Mumbai–Pune RailwayRailway station 4.3km away (Vadgaon)Limited bus connectivity nearby
Water & environment
River 1.1 km · PavanaWater body 1.2 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Layout Permit
Survey no. Gat No. 226, 244, 245 & 246
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.