Amar Adeshwar Infrastructure

Rajasthan

gethorizon.in/builders/amar-adeshwar-infrastructure

Amar Adeshwar Infrastructure has 6 projects on the public RERA record across 1 state, filed under 1 approving authority, first registered 2018 through 2021.

What they build
Residential 100%

Portfolio, summed

Everything the builder declared at registration, added up across the projects on the record.

6
Projects
1
City
2018–2021
On the record
1
Authorities
2,77,451 sq m
built-up declared
₹435.01 Cr
declared build cost

Every figure is drawn from the official RERA government registers — as each project declared it, not an independent measurement.

What they build

6projects
  • Residential6 100%

Where they build

  • Rajasthan6 projects

Who approves them 1 authority

  • Jodhpur Development Authority1 projects

The planning authorities that signed these projects off, read from each filing’s approval record — not every state files the approving body, so this covers the projects where it’s on record.

Track record over time

When their projects were registered, and when the filed pipeline is due to complete.

New projects each year

118019020521

Completion pipeline

127

By each project’s filed (or revised) possession year.

Timelineevery project, start → promised completion

The projects

6 on the record
Group Housing

INDRAPRASTH (PHASE 1)

Amar Adeshwar Infrastructure · Jodhpur

Apr 2021registered
Dec 2021target completion
Land area27,310 sq mCompletion deadline extended2 extensions on record — latest to 3 Dec 2021
Group Housing

INDRAPRASTH (PHASE 2)

Amar Adeshwar Infrastructure · Jodhpur

Apr 2021registered
Dec 2021target completion
Land area27,310 sq mCompletion deadline extended2 extensions on record — latest to 3 Dec 2021
Group Housing

INDRAPRASTH (PHASE 3)

Amar Adeshwar Infrastructure · Jodhpur

Apr 2021registered
Dec 2021target completion
Land area27,310 sq mCompletion deadline extended2 extensions on record — latest to 3 Dec 2021
Group Housing

INDRAPRASTH (PHASE-5)

Amar Adeshwar Infrastructure · Jodhpur

Apr 2021registered
Dec 2021target completion
Land area42,287 sq m
Group Housing

INDRAPRASTH (PHASE 4)

Amar Adeshwar Infrastructure · Jodhpur

Apr 2021registered
Dec 2021target completion
Land area42,287 sq m
Group Housing

INDRAPRASTH

Amar Adeshwar Infrastructure · Jodhpur

Nov 2018registered
Dec 2027target completion
Land area42,287 sq mCompletion deadline extended4 extensions on record — latest to 3 Dec 2027

Compiled from the official Rajasthan RERA government register— every project filed under this name that Horizon has read. Because the record identifies a builder by name, a common name can pool more than one firm; this page groups by name and does not assert that all projects share an owner. Dates are the filing’s registration and target completion, as published by the authority; nothing on this page is a rating, a ranking or a prediction.