Complete project overview

RERA Telangana · Registration filing
Units
10 units
Unit mix
5 × 3BHK, 5 × 2BHK
Saleable area
121–149 sq mper unit, as filed
Floors
5
Land area
418 sq m
Built-up area
1,070 sq m

Timeline

RERA approvedJan 2023
Proposed completionJan 2026
TodayJul 2026
Construction progress

80% overall, as filed

Podiums0%
OC-readiness0%
Excavation100%
Basement & plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

10 of 10 available
BuildingFloorTypeArea sq mAvailable
ADITI KRISHNA PRIME13BHKmortgaged1491 of 1
ADITI KRISHNA PRIME12BHK1211 of 1
ADITI KRISHNA PRIME23BHK1491 of 1
ADITI KRISHNA PRIME22BHK1211 of 1
ADITI KRISHNA PRIME33BHK1491 of 1
ADITI KRISHNA PRIME32BHK1211 of 1
ADITI KRISHNA PRIME42BHK1211 of 1
ADITI KRISHNA PRIME43BHK1491 of 1
ADITI KRISHNA PRIME53BHK1491 of 1
ADITI KRISHNA PRIME52BHK1211 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

ADITI AVENUES

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
21Projects
5Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
296 homeson the public record across 21 projects
33,486 sq mbuilt-up filed
19,883 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporationthis project11 of 21 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority9 of 21 projects
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 21 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
MADINAGUDA
Village
Madina Guda
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500049
North boundary
PLOT NO 92
East boundary
50 WIDE ROAD
South boundary
PLOT NO 90
West boundary
PLOT NO 82
What’s nearby
SchoolsNearest school 1.2km away · College or university 1.9km away
HealthcareHospital 1.2km away · Clinic within 2km
LifestylePark 1.4km away · Gym or sports centre 1.7km away · Swimming pool within 2km
ShoppingSupermarket 1.3km away
Getting around
Expressway 1.4 km · Allwyn - Gangaram Road Mumbai HighwayPrimary road 1.1 km · Gachibowli - Miyapur RoadRailway line 117 mRailway station 1.6km away (Hafeezpet)Limited bus connectivity nearby
Water & environment
Water body 660 m · Madinaguda Cheruvu
distances only — not a flood assessment
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit
Survey no. 32/1

The promised possession date (31 Jan 2026) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.