HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
49 units
Mix
25 × 2BHK · 12 × 3BHK · 12 × 1BHK
Booked
47 of 49 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,440 sq m
Floor area
5,374 sq m
Description
ADORA ETERNITY

Timeline

RERA registeredDec 2023
Project startedFeb 2024
Proposed completionDec 2028
TodayJul 2026
Construction progress

16% overall, as filed

Sanitary Fittings0%
Electrical Fittings0%
Staircases, Lifts Wells0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings10%
Slabs of Super Structure30%
Excavation100%
Basement(s) and Plinth100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

2 of 49 available
TypeArea sq mAvailable
2BHK621 of 1
2BHK651 of 12
3BHK840 of 12
2BHK560 of 12
1BHK310 of 12

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

ADORA HOMES PRIVATE LIMITED

CompanyPromoter type
Thrissur, KeralaBased in
No — the promoter declared this is a first projectDeclared prior experience
4Projects
1Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
182 homeson the public record across 4 projects
19,287 sq mbuilt-up filed
5,750 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Thrissur Municipal CorporationMunicipal Corporation3 of 4 projects
Puthur Grama PanchayatGrama Panchayatthis project1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
Kuttanellur P.O
Village
MARATHAKKARA
Taluk
Thrissur
District
Thrissur
Pincode
680014
Survey no.
11/84-1, 11/84-2, 11/85, 11/86
Patta no.
9112, 8380
What’s nearby
SchoolsNearest school 1.4km away
HealthcareNearest hospital 2.1km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 822 m · Salem - Kochi - Kanyakumari HighwayPrimary road 2.1 km · High RoadRailway line 2.4 kmRailway station 3.1km away (Ollur)Limited bus connectivity nearby
Water & environment
River 301 m · Manali RiverWater body 329 mCanal 841 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Puthur Grama Panchayat

Grama Panchayat
approved 10 Nov 2023 · 2 yrs ago
Building Permit no. SC3-BA(370555)/2023Survey no. 11/84-1, 11/84-2, 11/85, 11/86
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan SC3-BA(370555)/2023 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Grama Panchayat

A village-level local self-government (LSGI) that issues the permit — Kerala's most common approving body. It has approved 268 RERA projects across 13 districts about 1 in 6 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.