Complete project overview

GujRERA · Registration filing
Units
73 units
Mix
73 × 2 BHK Apartments & Shops
Carpet area
17–59 sq mper-unit range, as filed
Parking
3 spaces
Land area
2,259 sq m
Affordable housing
Yes — registered under affordable housingprice caps & eligibility apply

Timeline

Project startedJan 2023
RERA registeredMar 2023
Proposed completionDec 2027
TodayJul 2026
Construction progress

75% overall, as filed

Overall % complete as filed with GujRERA, taken as the slowest of the project's blocks — a snapshot, not a live tracker. Where a BU permission is on record (section 04), that is the firmer completion signal.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

73 units across 1 batch
TypeArea sq mCount
2 BHK Apartments & Shops4973

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

GujRERA · Promoter registration

SKYLINE INFRASTRUCTURE

PARTNERSHIP FIRMPromoter type
Mehsana, GujaratBased in
5Projects
4Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
200 homeson the public record across 5 projects
6,803 sq mbuilt-up filed
6,053 sq mland declared
₹15.07 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 2 projects
Othersthis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

GujRERA · Registration filing
Taluka
Mahesana
District
Mehsana
Address
R S No.3/2, Nr. Sarkari Vasahat,Dhobighat Road, Mehsana
What’s nearby
Schools6 schools within 1km · 8 educational institutions within 1km · College or university 665m away
HealthcareHospital 567m away · 2 clinics within 1km · Doctor's clinic within 1km
LifestylePark 605m away
ShoppingSupermarket 657m away · Mall 1.2km away · Bank 811m away
Getting around
Expressway 423 mPrimary road 581 mRailway line 1.3 kmRailway station 1.4km away (Mahesana Junction)Bus stop within 1km
Water & environment
Water body 576 m · Swami Vivekanand LakeRiver 785 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹6.07 Cr declared to build 73 flats. What that works out to:

₹6.15 Lakh – ₹12.00 Lakhdeclared unit pricerange on the filing — not a live asking price
₹8.31 Lakhdeclared cost per flatall-in — land + construction
₹1,565/sq ftof carpet area₹16,845/sq m
22%of the cost is land₹541/sq ft of land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

GujRERA · Approved building plan

Others

Building Permitapproved 6 Mar 2023 · 3 yrs ago
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The approving authority

The body that sanctioned this project. It has approved 2,653 RERA projects across 26 talukas about 1 in 6 in Gujarat.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Complaints — GujRERA does not publish a complaints register. This read cannot speak to them either way.