Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
2
Parking
29 spaces
Land area
799 sq m
Sanctioned built-up
2,012 sq m

Timeline

RERA registeredJul 2025
Proposed completionMay 2028
TodayJul 2026
Construction progress
Internal finishes0%
Flat fit-out0%
External finishes0%
OC-readiness0%
Solid Waste Manage…0%
Superstructure40%
Stairs & lifts47%
Excavation100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

VS DEVELOPERS

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
5Projects
5Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
26 homes · 107 plotson the public record across 5 projects
6,547 sq mbuilt-up filed
22,379 sq mplotted area
26,123 sq mland declared
₹1.16 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Directorate of Town & Country Planning (DTCP)Town & Country Planning (DTCP)1 of 4 projects
Hospete Urban Development AuthorityUrban Development Authority1 of 4 projects
Maharashtra Housing and Area Development Authority (MHADA)Housing Authority1 of 4 projects
Municipal Corporation of Greater MumbaiMunicipal Corporationthis project1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Malad
Taluka
Borivali
District
Mumbai Suburban
Pincode
400064
Survey no.
515A
North boundary
CTS 516
East boundary
CTS 515/B
South boundary
AMRAPALI CHS CTS NO 513
West boundary
TUREL PAKHADI ROAD
What’s nearby
Schools1 school within 500m · 4 educational institutions within 1km · College or university 1.1km away
HealthcareHospital 275m away · 11 clinics within 1km · Pharmacy within 1km
LifestylePark 1.1km away · Gym or sports centre 882m away · 11+ restaurants and cafes within 1km
ShoppingSupermarket 726m away · Mall 743m away · Bank 332m away
Getting around
Expressway 1.7 kmPrimary road 456 m · Swami Vivekanand RoadRailway line 645 m · Western Railway (Slow)Railway station 692m away (Malad)Bus stop within 1km
Water & environment
Water body 571 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 515A
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.