Complete project overview

TNRERA · Registration filing
Description
Construction of G.F + 4th Floor residential building and additional construction with 360 dwelling units at Block-A, D & F (3 Blocks) comprised in S.Nos.381/1A, 1B1, 1B2, 3A, 3B, 3C, 383/1A, 1B, 1C, 3, 384 to 390, 393/12A1, 12A2, 12A3, 12A4, 12A5, 12A6, 12A7, 15A2, 15B1, 15B2, 15B3, 15B4, 394 (except 394/15), 437 (except 437/5), 438, 439, T.S.Nos.390/2Apt, 2B1, 2B2, 2B3, 2B4, 3A, 3B, 4, 5, 6A, 6B, 7A, 7B, 8, 394/2Fpt, 3pt, 4pt & 6pt of Fovindapuram Hamlet, Segundram Village, Chengalpattu Taluk, Kancheepuram District.
Registration no.
TN/01/Building/0297/2022

Timeline

RERA registeredAug 2022
Proposed completionDec 2025
TodayJul 2026
02

Builder’s track record

TNRERA · Promoter registration

Ashiana Housing Ltd.

Ashiana Housing Ltd.Promoter
6Projects
1City
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
530 homeson the public record across 6 projects
3,16,564 sq mbuilt-up filed
₹391.80 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
MunicipalityMunicipality2 of 4 projects
Town & Country Planning (DTCP)Town & Country Planning (DTCP)this project2 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

TNRERA · Registration filing
04

Planning authority

TNRERA · Approved building plan

Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Planning Permissionapproved 5 Aug 2022 · 3 yrs ago

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Town & Country Planning (DTCP)

Town & country planning

Has approved 756 RERA projectsabout 1 in 5 in Tamil Nadu.

Builders
467
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.