Complete project overview

RAJ-RERA · Registration filing
Land area
3,288 sq m
Completion deadline extended
3 extensions on record — latest to 30 Sep 2022declared reason: force majeure
Description
1. Earlier the proposed project ATHARV APPARTMENT having registration no. RAJ/P/2017/499 registered with RERA with the name of promoter as M/S OM SOKHAL BUILDERS LLP. Later on, M/S SHP HOME LLP has purchased the said project from the promoter (sale deed of which attached in Legal Tile Documents of online form) and applied for the registration of new project on the same land and having same building and other amenities, accordingly the earlier project with registration no. RAJ/P/2017/499 was “revoked” and the new registration of project in RERA applied by the M/S SHP HOME LLP as promoter and consent of 2/3rd allottees regarding same was submitted in RERA for further processing of registration along with hard copies of project documents. 2. Name of the project has changed from "Atharv Appartment" to "Atharv Apartment" on 28-07-2020 and revised registration certificate has issued accordingly. Also, the project total area and phase area have changed to 3287.91sq.mt. from 3289.21sq.mt. and should be read accordingly. And Apartment Type Design column also modified accordingly to the given application by the promoter. This bears the approval of Honorable Chairman SirAs per remark the correct phase area has been rectified in Land Details of Registering Project.

Timeline

Construction startApr 2017
RERA registeredJun 2020
Proposed completionMar 2021
TodayJul 2026
02

Builder’s track record

RAJ-RERA · Promoter registration

SHP HOME LLP

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2020–2021Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
C-8, Eden Garden Scheme, C-Block, Sikar Road, Rajawas, AMER, Jaipur, 302013
Village
Rajawas
Taluka
AMER
District
Jaipur
Pincode
302013
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.1km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 441 mRailway line 3.4 kmNo metro or railway within 5kmLimited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹25.33 Cr declared. What that works out to:

12%of the cost is land

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 9 Jun 2020 · 6 yrs ago

The promised possession date (31 Mar 2021) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.