Jaivilas

RAJ/P/2017/229 · RAJ-RERA · https://gethorizon.in/projects/jaivilas-jaipur-376ryoq1

01

Complete project overview

RAJ-RERA · Registration filing
Project name
Jaivilas
Land area
20,398 sq m
Completion deadline extended
3 extensions on record — latest to 31 Jul 2022declared reason: force majeure
Description
As per Applicant request application w.r.t. Extension of Estimated Finished date and further to the approval of Hon'ble Chairman on 07-01-2020, the estimated finished date has been changed from 31-07-2020 to 31-12-2020.Therefore revised estimated finished date should be now read as 31-12-2020. Estimated finished date updated on 08-01-2020.

Timeline

Construction startMay 2014
RERA registeredSep 2017
Proposed completionDec 2020
TodaySep 2026
02

Builder’s track record

RAJ-RERA · Builder registration

Apeksha Infraprojects Private Limited

OrganisationPromoter type
Jaipur, RajasthanBased in
1Projects
1City
2017–2020Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RAJ-RERA · Registration filing
Address
1, Suncity, Sikar Road, nindar, Jaipur, Jaipur, 302013
Village
nindar
Taluka
Jaipur
District
Jaipur
Pincode
302013
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 386 mRailway line 3.2 kmNo metro or railway within 5kmLimited bus connectivity nearby
Price analysisdeclared build cost — not a sale price

₹90.07 Cr declared. What that works out to:

4%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan registration department

In Rajasthan it’s called the DLC rate.

No government guidance rate is shown for this project.

Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RAJ-RERA · Approved building plan
Building Permitapproved 27 Sep 2017 · 9 yrs ago

The promised possession date (31 Dec 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

07

Other projects nearby

The register · within 25 km

273 residential projects still under way within 25 km. Step out ring by ring:

Of the 41 projects the radar draws within 6 km — every kind, every stage — 9 are residential projects still under way. This list keeps only those, and looks further out.

3 projects within 1 km — showing the nearest 3.

550 m awayGroup Housing

Ashiana Greens Phase 6

The Green Triveni Developer · AMER · Jaipur

Apr 2023registered
Dec 2030target completion
Declared cost₹4.82 CrScale20 flatsAuthorityRAJ-RERA
590 m awayGroup Housing

Ashiana Greens Phase 4

The Green Triveni Developer · AMER · Jaipur

Jan 2023registered
Dec 2027target completion
Declared cost₹4.79 CrScale20 flatsAuthorityRAJ-RERA
670 m awayGroup Housing

Ashiana Greens Phase 5

The Green Triveni Developer · AMER · Jaipur

Mar 2023registered
Dec 2028target completion
Declared cost₹4.80 CrScale20 flatsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.