HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
19
Buildings
2
Parking
112 spaces
Land area
3,860 sq m
Sanctioned built-up
17,322 sq m
Recreational open space
324 sq m

Timeline

RERA registeredApr 2021
Proposed completionMar 2025
TodayJul 2026
Construction progress
Flat fit-out0%
Street Lighting0%
Aggregate area of …0%
Landscaping & Tree…40%
Internal Roads & F…50%
Storm Water Drains50%
Solid Waste Manage…60%
External finishes70%
OC-readiness70%
Water Supply70%
Treatment And Disp…70%
Sewerage (Chamber,…75%
Water conservation…75%
Fire protection an…85%
Internal finishes90%
Stairs & lifts95%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Parmaz Green Realty LLP

PartnershipPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2021–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Keshavnagar-Mundwa
Taluka
Pune City
District
Pune
Pincode
411036
Survey no.
84 1 A, 1 H, 2 A,2 H
North boundary
84
East boundary
84
South boundary
84
West boundary
83
What’s nearby
SchoolsNearest school 1.2km away · Library 1.9km away
HealthcareHospital 547m away · 3 clinics within 1km
Lifestyle2 parks within 500m · Gym or sports centre 1.8km away
ShoppingSupermarket 1.8km away · Mall 1.7km away
Getting around
Expressway 526 mPrimary road 247 m · Mundhwa RoadRailway line 965 m · Pune - Daund Railway LineRailway station 1.4km away (Hadapsar Railway Station)Bus stop within 1km
Water & environment
River 581 m · Mula-MuthaWater body 749 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 84 1 A, 1 H, 2 A,2 H

The promised possession date (31 Mar 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Municipal Corporation

Municipal corporation

Has approved 1,863 RERA projectsabout 1 in 11 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,351
On record
9,749 flats · 439 plots
Reach
3 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.