Complete project overview

K-RERA · Registration filing
Units
189 units
Mix
113 × 2BHK · 76 × 3BHK
Booked
124 of 189 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
5,072 sq m
Floor area
19,918 sq m
Description
DD HIPPODROME

Timeline

Project startedMay 2022
RERA registeredMay 2022
Proposed completionDec 2026
TodayJul 2026
Construction progress

14% overall, as filed

Stilt Floor0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings0%
Sanitary Fittings0%
Electrical Fittings0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Staircases, Lifts Wells15%
Slabs of Super Structure45%
Basement(s) and Plinth65%
Excavation100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

65 of 189 available
TypeArea sq mAvailable
2BHK5238 of 76
3BHK611 of 17
2BHK504 of 19
3BHK512 of 2
3BHK610 of 17
3BHK593 of 4
3BHK6017 of 36
2BHK500 of 18

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

DESAI HOMES

PartnershipPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
8Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
961 homeson the public record across 8 projects
1,34,411 sq mbuilt-up filed
31,384 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Choornikkara Grama Panchayat ErnakulamLocal body (LSGI)1 of 7 projects
KottayamLocal body (LSGI)1 of 7 projects
Kozhikkode Municipal CorporationMunicipal Corporation1 of 7 projects
MangalapuramLocal body (LSGI)this project1 of 7 projects
Mangalapuram Grama PanchayatGrama Panchayat1 of 7 projects
ThrikkakkaraLocal body (LSGI)1 of 7 projects
Thrikkakra MunicipalityMunicipality1 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
EDAVILAKOM ROAD
Village
VEILOOR
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695302
Survey no.
S-1439/29,2657/1,R-245/3-7
Patta no.
16648
What’s nearby
SchoolsNearest school 1.3km away
HealthcareHospital 1.9km away · 1 clinic within 1km
LifestylePark 1.6km away
ShoppingSupermarket 487m away · Mall 1.2km away · Bank 525m away
Getting around
Expressway 1.6 km · Salem - Kochi - Kanyakumari RoadPrimary road 4.2 km · Kattaikonam - Chandavila - VetturoadRailway line 389 mRailway station 923m away (Murukkampuzha)2 bus stops within 500m
Water & environment
Water body 351 mCanal 1.7 km · Parvathy Puthanar
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Mangalapuram

Local body (LSGI)
approved 25 Mar 2022 · 4 yrs ago
Building Permit no. A3-BA(/4764/2021)/2022Survey no. S-1439/29,2657/1,R-245/3-7
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan A3-BA(/4764/2021)/2022 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

The local self-government (LSGI)

The local body that sanctioned this project. It has approved 404 RERA projects across 14 districts about 1 in 4 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.