01

Complete project overview

TNRERA · Registration filing
Description
Registration for Stilt Floor + 5 Floors Residential Apartment Building with 25 Dwelling Units at Comprised in T.S.No.2 (S.F.No.121/3B Pt), Ward No.D, Block No: 33 of Kavundampalayam Village, Coimbatore North Taluk, Coimbatore District.
Registration no.
TN/11/Building/0002/2025

Timeline

RERA registeredJan 2025
Proposed completionDec 2027
TodaySep 2026
02

Builder’s track record

TNRERA · Builder registration

Dhiya Foundation Pvt Ltd

Dhiya Foundation Pvt LtdPromoter
14Projects
1Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
14 projectson the public record across 14 projects

These are sums of what the builder has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Municipal CorporationMunicipal Corporation8 of 14 projects
Town & Country Planning (DTCP)Town & Country Planning (DTCP)this project5 of 14 projects
Planning authority1 of 14 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Dhiya Foundation Pvt Ltd— the full portfolio →

03

Location

TNRERA · Registration filing
What’s nearby
Schools1 school within 500m
HealthcareHospital 391m away · 2 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km
ShoppingSupermarket 1.7km away · Bank 312m away · ATM within 500m
Getting around
Expressway 1.7 km · Coimbatore - Mettupalayam road kavundampalayam FlyoverPrimary road 705 m · Thadagam RoadRailway line 2.1 kmRailway station 3.2km away (Coimbatore North)Bus stop within 1km
Water & environment
Water body 2.1 km
distances only — not a flood assessment
04

Government Guidance Rate

Tamil Nadu registration department

In Tamil Nadu it’s called the guideline value.

No government guidance rate is shown for this project.

Tamil Nadu publishes street-level guideline values; its full schedule isn't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

TNRERA · Approved building plan

Town & Country Planning (DTCP)

Town & Country Planning (DTCP)
Planning Permissionapproved 7 Jan 2025 · 1 yr ago
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Town & Country Planning (DTCP)

Town & country planning

Has approved 756 RERA projectsabout 1 in 5 in Tamil Nadu.

Builders
467
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by TNRERA

07

Other projects nearby

The register · within 25 km

119 residential and mixed-use projects still under way within 25 km. Step out ring by ring:

Of the 50 projects the radar draws within 6 km — every kind, every stage — 46 are residential and mixed-use projects still under way. This list keeps only those, and looks further out.

2 projects within 1 km — showing the nearest 2.

790 m away

MR RESIDENCY

JMJ HOUSING LIMITED

Jul 2024registered
Sep 2028target completion
AuthorityTNRERA
840 m away

ATLANTIC CITY

TNCD LLP

Feb 2026registered
Dec 2030target completion
AuthorityTNRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — TNRERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — TNRERA does not publish a complaints register. This read cannot speak to them either way.
  • Escrow — TNRERA does not publish escrow declarations. Whether buyer money is ring-fenced cannot be read here.