Complete project overview

MahaRERA · Registration filing
Floors
9
Buildings
2
Parking
92 spaces
Land area
694 sq m
Sanctioned built-up
2,791 sq m

Timeline

RERA registeredJan 2024
Proposed completionDec 2027
TodayJul 2026
Construction progress
Podiums0%
External finishes0%
OC-readiness0%
Water Supply0%
Water conservation…0%
Flat fit-out10%
Sewerage (Chamber,…40%
Stairs & lifts60%
Basement (if any)80%
Plinth80%
Internal finishes85%
Excavation100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SATYAJIT GOVIND LELE

IndividualPromoter type
Sangli, MAHARASHTRABased in
4Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
72 homeson the public record across 4 projects
6,214 sq mbuilt-up filed
2,464 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Sangli Miraj Kupwad (M Corp.)
Taluka
Miraj
District
Sangli
Pincode
416410
Survey no.
C S NO 1971 c
North boundary
C S NO 1971 B
East boundary
C S NO 1965 C S NO 1966A
South boundary
ROAD
West boundary
C S NO 1971 D C S NO 1971 A
What’s nearby
Schools1 school within 1km
HealthcareHospital 405m away · 9 clinics within 1km · Doctor's clinic within 1km
LifestylePark 1.6km away
ShoppingSupermarket 475m away
Getting around
Expressway 1.1 km · Sangli-Miraj RoadPrimary road 920 m · Shivaji RoadRailway line 1.8 kmRailway station 1.8km away (Miraj Junction)Limited bus connectivity nearby
Water & environment
Water body 673 m · Ganesh Talav
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.