HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Plots
5 plots
Mix
5 × Bangalow / Villas
Buildings
5
Land area
1,408 sq m
Floor area
747 sq m
Description
EASTBROOK BY VALLUVASSERY

Timeline

Project startedAug 2023
RERA registeredMay 2026
Proposed completionJul 2027
TodayJul 2026
Construction progress

69% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
The external plumbing and external plastering25%
The external plumbing and external plastering25%
The external plumbing and external plastering25%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Staircases, Lifts Wells50%
Installation of lifts, water pumps etc50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc75%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc75%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc75%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

5 of 5 available
TypeArea sq mAvailable
Bangalow / Villas1231 of 1
Bangalow / Villas1141 of 1
Bangalow / Villas1211 of 1
Bangalow / Villas1151 of 1
Bangalow / Villas1361 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

VALLUVASSERYBUILDERSPRIVATELTD

CompanyPromoter type
Ernakulam, KeralaBased in
No — the promoter declared this is a first projectDeclared prior experience
1Projects
1Cities
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
PAZHAKKAMATTOM
Village
THIRUVANIYOOR
Taluk
Kunnathunad
District
Ernakulam
Pincode
682308
Survey no.
9/110 S-67/3B R-326/10-2-3, S-R-326/10-2-1-2,S-R-326/10-2-1-3,326-10-2
Patta no.
2024/33434/07A/CNO9607,2024/33435/07/9653,2024/33437/07/9784,2023/35364/07/5925
What’s nearby
SchoolsNearest school 1.4km away · Library 1.0km away
HealthcareNearest hospital 2.2km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingSupermarket 1.1km away
Getting around
Expressway 2.3 km · Kochi - Madurai - Dhanushkodi RoadNo metro or railway within 5kmBus stop within 1km
Water & environment
Water body 488 mRiver 785 m · ChitrapuzhaCanal 1.6 km
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Thiruvaniyoor

Local body (LSGI)
approved 23 Aug 2025 · 11 mo ago
Layout Permit no. A3BA(184118)2025Survey no. 9/110 S-67/3B R-326/10-2-3, S-R-326/10-2-1-2,S-R-326/10-2-1-3,326-10-2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan A3BA(184118)2025 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

The local self-government (LSGI)

The local body that sanctioned this project. It has approved 404 RERA projects across 14 districts about 1 in 4 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.