Description
GALAXY EMERALD

Timeline

Project startedFeb 2016
RERA registeredMar 2022
Proposed completionNov 2022
TodayJul 2026
Construction progress

60% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings20%
Staircases, Lifts Wells70%
Overhead and Underground Water Tanks.70%
Slabs of Super Structure80%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

9 of 74 available
TypeArea sq mAvailable
1 2 3 BHK3,1819 of 74

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

GALAXY HOMES PVT LTD

CompanyPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
9Projects
1Cities
2022–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
714 homeson the public record across 9 projects
72,262 sq mbuilt-up filed
23,042 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kochi Municipal CorporationMunicipal Corporation6 of 9 projects
Thrikkakkara MunicipalityMunicipality2 of 9 projects
Cochin Municipal CorporationMunicipal Corporationthis project1 of 9 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
FATHIMA MATHA CHURCH ROAD
Village
ELAMKULAM
Taluk
Kanayannur
District
Ernakulam
Pincode
682020
Survey no.
516/1-2-16
Patta no.
33980
What’s nearby
SchoolsNearest school 1.2km away · 5 educational institutions within 1km · Library 664m away
HealthcareHospital 549m away · 10 clinics within 1km · Pharmacy within 500m
LifestylePark 690m away · Gym or sports centre 391m away · 65+ restaurants and cafes within 1km
ShoppingSupermarket 207m away · Mall 1.3km away · Convenience store within 500m
Getting around
Expressway 1.4 kmPrimary road 303 m · Sahodaran Ayyappan RoadRailway line 990 mMetro station 508m away (Elamkulam)3 bus stops within 500mAirport 4.4km away
Water & environment
Canal 255 mWater body 664 m · Temple Pond
distances only — not a flood assessment
Land, title & encumbrance
LitigationA litigation is declared on record — verify directly with K-RERA
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Cochin Municipal Corporation

Municipal Corporation
approved 6 Nov 2017 · 8 yrs ago
Building Permit no. KRP2-108/16(KRP/COC/43/16)Survey no. 516/1-2-16

The promised possession date (19 Nov 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan KRP2-108/16(KRP/COC/43/16) on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Cochin Municipal Corporation

Municipal corporation / municipality

Has approved 40 RERA projects2.6% of Kerala.

an apartments market98% apartments · 2% plotted layouts. Apartments like yours are this body's core business.

Builders
24
On record
1,429 flats · 19 plots
Since
2021

More apartment-heavy than Kerala overall — 98% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.