HORIZONMarkets
01

Complete project overview

UP-RERA · Registration filing
Units
141 units
Unit mix
79 × 1 BHK · 58 × 2 BHK · 4 × SHOP
Carpet area
15–62 sq mper unit, as filed
Floors
6
Blocks
2
Land area
5,473 sq m

Timeline

Project startedOct 2015
RERA registeredAug 2017
Proposed completionOct 2020
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

141 units across 28 batches
BuildingFloorTypeArea sq mCount
AGF1 BHK422
AGF1 BHK425
AGF2 BHK612
AGFSHOP154
A11 BHK424
A11 BHK425
A12 BHK612
A21 BHK424
A21 BHK425
A22 BHK612
A31 BHK424
A31 BHK425
A32 BHK612
A41 BHK424
A41 BHK425
A42 BHK612
B11 BHK426
B12 BHK628
B21 BHK426
B22 BHK478
B31 BHK426
B32 BHK628
B41 BHK426
B42 BHK628
B51 BHK426
B52 BHK628
B61 BHK426
B62 BHK628

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

SKYNET INFRAVENTURES PVT. LTD.

CompanyPromoter type
4Registered projects
4Projects
1City
2017–2021Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
237 homes · 23 plotson the public record across 4 projects
3,709 sq mplotted area
14,544 sq mland declared
₹24.74 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Prayagraj
Tehsil
Karchhana
Site access
plot no 15 mauza dhanua , rewa road Allahabad
What’s nearby
Schools3 schools within 1km · 3 educational institutions within 1km
HealthcareHospital 400m away · 1 clinic within 1km
LifestylePark 1.3km away · Swimming pool within 2km
ShoppingNo supermarket within 2km · Mall 623m away · Convenience store within 1km
Getting around
Expressway 137 mRailway line 1.4 kmRailway station 2.5km away (Naini Junction)Limited bus connectivity nearby
Water & environment
Water body 1.1 km · MAMA BHANJA KA TALAB
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹9.72 Cr declared to build 141 flats. What that works out to:

₹6.89 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 7 Oct 2015 · 10 yrs ago
Building Permit no. 17

The promised possession date (6 Oct 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 17 on the approving authority’s portal to confirm the sanction.

Complaints register

None on record with UP-RERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.