HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
34
Buildings
12
Parking
419 spaces
Land area
48,504 sq m
Sanctioned built-up
1,03,984 sq m
Recreational open space
15,599 sq m

Timeline

RERA registeredDec 2020
Proposed completionJun 2028
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Stilt floor0%
Community Building…0%
Water conservation…0%
Aggregate area of …50%
Landscaping & Tree…60%
Open Parking70%
Street Lighting90%
Internal Roads & F…95%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Water Supply100%
Sewerage (Chamber,…100%
Storm Water Drains100%
Treatment And Disp…100%
Solid Waste Manage…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

PRAKHHYAT DWELLINGS LLP

PartnershipPromoter type
Mumbai Suburban, MAHARASHTRABased in
2Projects
1City
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,176 homeson the public record across 2 projects
1,62,630 sq mbuilt-up filed
80,139 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Bhiwandi (M Corp.)
Taluka
Bhiwandi
District
Thane
Pincode
421302
Survey no.
40/1/2 40/2 40/3 40/4 40/5 40/640/740/840/940/1040/11 40/12 40/13/1/A 40/13/2 42 43/1 43/2 43/3 44/1/1 44/1/2 44/2/1 44/2/2 44/2/3 44/3/1 44/3/2 44/4 44/5 44/6 45/2/1 45/3/1 45/4 45/7 45/8 45/9 58/20/1 58/20/2 58/21 58/22 84 128/3/4 128/3/5 129/1 181
North boundary
18 m wide DP road and TATA high tension line
East boundary
24 m wide DP road
South boundary
Survey number 41
West boundary
30 m wide DP road
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.4km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 317 m · Kalyan RoadPrimary road 317 mRailway line 2.4 kmRailway station 3.9km away (Bhivandi Road)4 bus stops within 500m
Water & environment
Water body 749 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Bhiwandi Nizampur City Municipal Corporation

Municipal Corporation
Building Permit
Survey no. 40/1/2 40/2 40/3 40/4 40/5 40/640/740/840/940/1040/11 40/12 40/13/1/A 40/13/2 42 43/1 43/2 43/3 44/1/1 44/1/2 44/2/1 44/2/2 44/2/3 44/3/1 44/3/2 44/4 44/5 44/6 45/2/1 45/3/1 45/4 45/7 45/8 45/9 58/20/1 58/20/2 58/21 58/22 84 128/3/4 128/3/5 129/1 181
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Bhiwandi Nizampur City Municipal Corporation

Municipal corporation

Has approved 34 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
25
On record
0 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation1 case on record, earliest 2023
Compliance1 non-compliance notice on record
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

5 complaints on MahaRERA’s register for this project 2 disposed, 3 still open.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.