Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Slabs of Super Structure50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Slabs of Super Structure50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Basement(s) and Plinth50%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Slabs of Super Structure50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Basement(s) and Plinth50%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Stilt Floor50%
Slabs of Super Structure50%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Sanitary Fittings50%
Electrical Fittings50%
Staircases, Lifts Wells50%
Overhead and Underground Water Tanks.50%
The external plumbing and external plastering50%
Completion of terraces floor each building50%
Installation of lifts, water pumps etc50%
Fire Fighting Fittings and Equipment50%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc50%
Slabs of Super Structure55%
The external plumbing and external plastering60%
Completion of terraces floor each building60%
Installation of lifts, water pumps etc60%
Fire Fighting Fittings and Equipment60%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc60%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings60%
Basement(s) and Plinth60%
Stilt Floor60%
Basement(s) and Plinth60%
Installation of lifts, water pumps etc60%
Fire Fighting Fittings and Equipment60%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc60%
Installation of lifts, water pumps etc60%
Fire Fighting Fittings and Equipment60%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc60%
Stilt Floor60%
Installation of lifts, water pumps etc60%
Fire Fighting Fittings and Equipment60%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc60%
Basement(s) and Plinth65%
The external plumbing and external plastering65%
Completion of terraces floor each building65%
Basement(s) and Plinth65%
Stilt Floor65%
Basement(s) and Plinth65%
Sanitary Fittings70%
Electrical Fittings70%
Staircases, Lifts Wells70%
Overhead and Underground Water Tanks.70%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings70%
Sanitary Fittings70%
Electrical Fittings70%
Staircases, Lifts Wells70%
Overhead and Underground Water Tanks.70%
The external plumbing and external plastering70%
Completion of terraces floor each building70%
Installation of lifts, water pumps etc70%
Fire Fighting Fittings and Equipment70%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc70%
Sanitary Fittings70%
Electrical Fittings70%
Staircases, Lifts Wells70%
Overhead and Underground Water Tanks.70%
The external plumbing and external plastering70%
Completion of terraces floor each building70%
Installation of lifts, water pumps etc70%
Fire Fighting Fittings and Equipment70%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc70%
Staircases, Lifts Wells70%
Overhead and Underground Water Tanks.70%
Sanitary Fittings70%
Electrical Fittings70%
Sanitary Fittings70%
Electrical Fittings70%
Slabs of Super Structure70%
Basement(s) and Plinth70%
Stilt Floor70%
Slabs of Super Structure70%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings70%
Sanitary Fittings70%
Electrical Fittings70%
Sanitary Fittings75%
Electrical Fittings75%
The external plumbing and external plastering75%
Completion of terraces floor each building75%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings75%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings80%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings80%
Staircases, Lifts Wells80%
Overhead and Underground Water Tanks.80%
Basement(s) and Plinth80%
Basement(s) and Plinth80%
Stilt Floor80%
Staircases, Lifts Wells80%
Overhead and Underground Water Tanks.80%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings85%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings85%
The external plumbing and external plastering85%
Completion of terraces floor each building85%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings85%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings85%
Basement(s) and Plinth90%
Stilt Floor90%
Slabs of Super Structure90%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Excavation100%
Excavation100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Excavation100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Excavation100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Excavation100%
Excavation100%
Excavation100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Excavation100%
Excavation100%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%