HAWARE IPSA

P51800019601 · MahaRERA · https://gethorizon.in/projects/haware-ipsa-kurla-ac9ioaj1

01

Complete project overview

MahaRERA · Registration filing
Units
72 units
Mix
32 × 1.5 BHK · 32 × 2 BHK · 5 × Shop · 3 × 1 BHK
Carpet area
8–57 sq mper-unit range, as filed
Floors
19
Buildings
2
Parking
52 spaces
Land area
827 sq m
Sanctioned built-up
4,159 sq m

Timeline

RERA registeredFeb 2019
Proposed completionAug 2023
TodaySep 2026

Find your flat

Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.

72 units across 8 batches
TypeArea sq mCount
Shop81
Shop451
1 BHK393
1.5 BHK4332
2 BHK5732
Shop271
Shop261
Shop91

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

MahaRERA · Builder registration

Haware Builders Private Limited

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
1Projects
1City
2019–2023Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Kurla
Taluka
Kurla
District
Mumbai Suburban
Pincode
400075
Survey no.
CTS No 185
North boundary
Proposed 12 20 Meter Road
East boundary
Building No 74
South boundary
Building No 76
West boundary
Building No 77
What’s nearby
Schools1 school within 500m
HealthcareHospital 86m away · 20 clinics within 1km · Pharmacy within 1km
Lifestyle1 park within 500m · Gym or sports centre 310m away · 18+ restaurants and cafes within 1km
ShoppingSupermarket 1.5km away · Bank 333m away
Getting around
Expressway 881 m · Kamraj Nagar FlyoverPrimary road 592 m · V B Phadke MargRailway line 234 m · Central Railways Fast LineRailway station 257m away (Ghatkopar)7 bus stops within 500m
Water & environment
Water body 1.5 km · Trombay Creek
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Mumbai's ready reckoner is addressed by city survey (CTS) number inside a named village, and this filing declares neither — its village field holds a ward or a taluka. Naming one of the zones around it would be a guess, and inside a single division the rates run three-fold.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

06

Other projects nearby

The register · within 25 km

4,755 residential projects still under way within 25 km. Step out ring by ring:

73 projects within 1 km — showing the nearest 6.

KurlaOthers

SHUBHAM AVENUE CHS LTD

AVVAD ICONS LLP

Oct 2022registered
Dec 2026target completion
Scale258 flatsAuthorityMahaRERA
GhatkoparResidential / Group Housing

90 NIRVAANA

SHREE DHAM DEVELOPERS

Jul 2023registered
Jun 2027target completion
Scale75 flatsAuthorityMahaRERA
GhatkoparResidential / Group Housing

VISAVA HARMONY

Best Super Edge Construction LLP

Aug 2024registered
Mar 2027target completion
Government Guidance Rate₹1,35,871/sq ydAuthorityMahaRERA
GhatkoparResidential / Group Housing

Shreeji Laxmi

SHREEJI LIFESPACES GROUP

Jun 2024registered
Dec 2027target completion
Government Guidance Rate₹1,35,871/sq ydAuthorityMahaRERA
GhatkoparResidential / Group Housing

SAJAY AVENUE 92

SAJAY DEVELOPER

May 2025registered
Jun 2028target completion
Scale102 flatsAuthorityMahaRERA
GhatkoparResidential / Group Housing

DIVINE ULTIMUS

SHREE DHAM DEVELOPERS

Jun 2024registered
Dec 2027target completion
Scale86 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.