Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Overhead and Underground Water Tanks.30%
Slabs of Super Structure45%
Staircases, Lifts Wells45%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Per-activity completion % from the builder's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.
Find your flat
Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
108 of 108 available
TypeArea sq mAvailable
3BHK7816 of 16
2BHK482 of 2
2BHK612 of 2
2BHK5432 of 32
2BHK5516 of 16
3BHK7816 of 16
2BHK552 of 2
2BHK534 of 4
2BHK5918 of 18
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the builder declared — not a live booking system.
Complete project overview — done
02
Builder’s track record
K-RERA · Builder registration
SHWAS BUILDERS AND DEVELOPERS PVT LTD
CompanyPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
SchoolsNearest school 1.2km away · College or university 500m away · Library 522m away
HealthcareHospital 366m away · 3 clinics within 1km · Pharmacy within 500m
LifestyleNo parks within 2km · Gym or sports centre 1.4km away
ShoppingSupermarket 1.4km away · Mall 1.5km away · Convenience store within 500m
Getting around
Expressway 2.0 km · Kochi - Dhanushkodi RoadPrimary road 398 m · Ettumanoor - Ernakulam RoadRailway line 1.6 kmRailway station 2.0km away (Tripunittura)2 bus stops within 500m
Water & environment
Water body 298 m
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the builder at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
Location — done
04
Government Guidance Rate
Kerala registration department
In Kerala it’s called the fair value.
No government guidance rate is shown for this project.
Kerala's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.
That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.
Government Guidance Rate — done
05
Planning authority
K-RERA · Approved building plan
Muncipality
Local body (LSGI)
approved 6 May 2019 · 7 yrs ago
Building Permit no. PW4-BA(86868)/2019 (PW4/BA/322/18-19)Survey no. 52/2,53,54,55/2,56/3,58/2,59/2,62/2
The promised possession date (11 Aug 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.
The occupancy certificate — the proof that isn’t here
An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.
Verify it yourself — look up plan PW4-BA(86868)/2019 (PW4/BA/322/18-19) on the approving authority’s portal to confirm the approval.
The approving body, at scale
The local self-government (LSGI)
The local body that approved this project. It has approved 404 RERA projects across 14 districts — about 1 in 4 in Kerala.
Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.
Planning authority — done
06
Complaints & litigation
K-RERA · public record
Complaints register
Not published. K-RERA doesn’t publish a complaints register in the record Horizon reads.
So there is nothing to count here — which is not the same as nothing having been filed.
What the builder declared
Declared to K-RERA
Litigation
None declared in this filing
Only what the builder declared, or what K-RERA records itself, can appear here — a case filed elsewhere and never declared would not.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with K-RERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
07
Other projects nearby
The register · within 25 km
185 residential projects still under way within 25 km. Step out ring by ring:
No government guidance rate could be matched to this project from Kerala's published schedules.
05Planning authority
K-RERA: the approved building plan, as filed.
The approving body's other projects: counted by Horizon across the register.
06Complaints & litigation
K-RERA's public record lists no complaints or litigation for this project.
07Other projects nearby
The RERA-registered projects Horizon holds within 25 km of these coordinates.
Compiled by Horizon from public records. Each fact is reproduced as its source publishes it, and Horizon does not verify filings on the ground. The live record: gethorizon.in/projects/highness-heights-thekkumbhagom-ernakulam-o6ntogp2.
Horizon does not rate, review, score or signal, and it gives no verdict, opinion or forecast. Its only aim is to seek the truth through data: what the public record says, where each fact comes from, and where the record is silent. Nothing in this document is legal, financial or investment advice; what to make of it is yours to decide.