IRISH ORISON

PM1290002500893 · MahaRERA · https://gethorizon.in/projects/irish-orison-sangli-miraj-kupwad-m-ws4ecfky

01

Complete project overview

MahaRERA · Registration filing
Units
89 units
Floors
24
Buildings
2
Parking
90 spaces
Land area
1,719 sq m
Sanctioned built-up
9,709 sq m

Timeline

RERA registeredSep 2025
Proposed completionDec 2032
TodaySep 2026
Construction progress
Plinth0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Open Parking0%
Basement (if any)50%
Excavation100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

CHAITANYA CONSTRUCTIONS

PartnershipPromoter type
Sangli, MAHARASHTRABased in
1Projects
1City
2025–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Sangli Miraj Kupwad (M Corp.)
Taluka
Miraj
District
Sangli
Pincode
416416
Survey no.
C S NO 27/1
North boundary
vakharbahg cts no 26/b and 26/a 1/a and b
East boundary
collector bungalow to amrai main gate road
South boundary
vakharbhag cst no 28 28/1 28/2 28/3 28/11 and 28/4
West boundary
road and vakharbahg cts no 26/b
What’s nearby
Schools1 school within 1km
HealthcareHospital 315m away · 4 clinics within 1km · Doctor's clinic within 1km
LifestylePark 554m away · Gym or sports centre 455m away
ShoppingNo supermarket within 2km
Getting around
Expressway 245 m · Azad ChowkPrimary road 211 m · Soni-Sangli RoadRailway line 1.4 kmRailway station 1.7km away (Sangli)Limited bus connectivity nearby
Water & environment
River 704 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Sangli Miraj Kupwad Municipal Corporation

Municipal Corporation
Building Permit
Survey no. C S NO 27/1
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Sangli Miraj Kupwad Municipal Corporation

Municipal corporation

Has approved 48 RERA projects0.2% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
44
On record
274 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

123 residential projects still under way within 25 km. Step out ring by ring:

Of the 423 projects the radar draws within 6 km — every kind, every stage — 71 are residential projects still under way. This list keeps only those, and looks further out.

6 projects within 1 km — showing the nearest 6.

160 m awayMixed

Shriram Vijay

Laxmi Udyog Samuha · Sangli Miraj Kupwad · Miraj

Feb 2026registered
Jun 2028target completion
Scale43 flatsAuthorityMahaRERA
340 m awayOthers

SHUBHAM EXOTICA

SRIVARI SHUBHA DEVELOPERS LLP · Sangli Miraj Kupwad · Miraj

Jul 2024registered
Dec 2027target completion
Scale39 flatsAuthorityMahaRERA
460 m awayOthers

SHRIRAM SOLITAIRE

Shriram Solitaire · Sangli Miraj Kupwad · Miraj

Mar 2024registered
Dec 2027target completion
Scale68 flatsAuthorityMahaRERA
480 m awayOthers

NARAYAN HEIGHTS

PRATHAM DEVELOPERS · Sangli Miraj Kupwad · Miraj

Mar 2025registered
Feb 2029target completion
Scale32 flatsAuthorityMahaRERA
620 m awayOthers

AVR SQUARE

GSJ INFRASTRUCTURE LLP · Sangli Miraj Kupwad · Miraj

Apr 2025registered
Dec 2027target completion
Scale21 flatsAuthorityMahaRERA
970 m awayOthers

SKY PALACE

AKSHAY NUCLEAR LLP · COLLEGE CORNER · Miraj

May 2023registered
Jun 2027target completion
Scale53 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.