HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
50 units
Mix
34 × 3BHK · 15 × 2BHK · 1 × 4BHK
Booked
50 of 50 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
2,190 sq m
Floor area
7,139 sq m
Description
Kalyan Divinity

Timeline

Project startedOct 2020
RERA registeredJul 2021
Proposed completionJun 2025
TodayJul 2026
Construction progress

85% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 50 available
TypeArea sq mAvailable
2BHK660 of 3
3BHK800 of 2
3BHK1180 of 5
3BHK930 of 2
2BHK700 of 1
3BHK850 of 2
3BHK1120 of 2
2BHK750 of 5
3BHK990 of 1
2BHK710 of 6
3BHK1700 of 1
4BHK1520 of 1
3BHK1130 of 6
3BHK750 of 2
3BHK970 of 5
3BHK1010 of 6

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

Kalyan Developers

PartnershipPromoter type
Thiruvananthapuram, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
22Projects
2Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,318 homes · 33 plotson the public record across 22 projects
2,48,218 sq mbuilt-up filed
61,310 sq mplotted area
1,26,898 sq mland declared
₹48.80 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
ThrissurLocal body (LSGI)3 of 22 projects
Thrissur Municipal CorporationMunicipal Corporation3 of 22 projects
TrivandrumLocal body (LSGI)3 of 22 projects
Kochi Municipal CorporationMunicipal Corporation2 of 22 projects
Cheranellore Grama PanchayatGrama Panchayat1 of 22 projects
CochinLocal body (LSGI)1 of 22 projects
KaiparambLocal body (LSGI)1 of 22 projects
Kalburgi Urban Development AuthorityUrban Development Authority1 of 22 projects
KozhikodeLocal body (LSGI)1 of 22 projects
Kozhikode Muncipal Municipal CorporationMunicipal Corporation1 of 22 projects
ThiruvananthapuramLocal body (LSGI)1 of 22 projects
ThiruvanthapuramLocal body (LSGI)1 of 22 projects
TriruvanthapuramLocal body (LSGI)this project1 of 22 projects
Vadodara Municipal CorporationMunicipal / Corporation1 of 22 projects
Vadodara Urban Development AuthorityUrban Development Authority1 of 22 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
SreeVaraham, Enchakkal Road, Near subhash Nagar, Vallakadavu P.O, Thiruvananthapuram
Village
PETTAH
Taluk
THIRUVANANTHAPRUAM
District
Thiruvananthapuram
Pincode
695008
Survey no.
1632/3, 1632/1, 1633/1, 1633/2, 1639/3, 1639/1
Patta no.
23371,22923,22329,22246
What’s nearby
Schools2 schools within 1km · 4 educational institutions within 1km · Library 375m away
HealthcareHospital 201m away · 2 clinics within 1km · Pharmacy within 500m
LifestylePark 1.3km away · Gym or sports centre 555m away · 29+ restaurants and cafes within 1km
ShoppingSupermarket 512m away · Mall 510m away · Convenience store within 1km
Getting around
Expressway 420 mPrimary road 137 mRailway line 1.4 kmRailway station 1.8km away (Thiruvananthapuram Central)5 bus stops within 500m
Water & environment
Canal 9 mRiver 117 mWater body 272 m · Sreevaraham Kulam
distances only — not a flood assessment
Land, title & encumbrance
Land ownershipBuilt on land that includes third-party owners — a landowner (joint-development) arrangement is declared; confirm the title and your share
As declared by the promoter at registration — a RERA self-declaration, not an authority's independent finding. A flagged line is worth verifying against the title documents; it is not a verdict.
04

Planning authority

K-RERA · Approved building plan

Triruvanthapuram

Local body (LSGI)
approved 20 Mar 2020 · 6 yrs ago
Building Permit no. FE2/BA/42/19Survey no. 1632/3, 1632/1, 1633/1, 1633/2, 1639/3, 1639/1

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan FE2/BA/42/19 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

The local self-government (LSGI)

The local body that sanctioned this project. It has approved 404 RERA projects across 14 districts about 1 in 4 in Kerala.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.