Complete project overview

MahaRERA · Registration filing
Floors
4
Buildings
4
Parking
51 spaces
Land area
1,972 sq m
Sanctioned built-up
3,467 sq m

Timeline

RERA registeredMay 2023
Proposed completionNov 2026
TodayJul 2026
Construction progress
Podiums0%
Flat fit-out0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Solid Waste Manage…0%
Water conservation…0%
Electrical meter r…0%
Open Parking0%
External finishes20%
Internal finishes50%
Stairs & lifts80%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

S J DEVELOPERS

PartnershipPromoter type
Pune, MAHARASHTRABased in
5Projects
4Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
16 homes · 14 plotson the public record across 5 projects
6,922 sq mbuilt-up filed
37,130 sq mplotted area
41,202 sq mland declared
₹5.50 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Bhavnagar Municipal CorporationMunicipal / Corporation2 of 5 projects
BMRDA - Bangalore Metropolitan Region Development AuthorityUrban Development Authority1 of 5 projects
Pune Municipal Corporation, PuneMunicipal Corporation1 of 5 projects
Saswad Municiple Councilthis project1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Sasvad (M Cl)
Taluka
Purandhar
District
Pune
Pincode
412301
Survey no.
Surve No. 9/5/6/7/1/2
North boundary
20 FEET ROAD
East boundary
PLOT NO A5 OF SANGITA JAGTAP LAND
South boundary
SURVE NO 6 AND 7 OF 2
West boundary
PLOT NO 12 OF YAMUNABAI GAIKWAD LANF
What’s nearby
SchoolsNo schools within 2km · College or university 1.2km away
HealthcareHospital 499m away
LifestylePark 1.0km away · Swimming pool within 2km
ShoppingSupermarket 764m away
Getting around
Expressway 564 m · Pune Saswad RoadPrimary road 916 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 1.9 kmRiver 2.2 km · Karha River
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Saswad Municiple Council

Building Permit
Survey no. Surve No. 9/5/6/7/1/2
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.