HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
21 units
Unit mix
21 × 2BHK
Saleable area
29–88 sq mper unit, as filed
Floors
5
Land area
736 sq m
Built-up area
1,766 sq m
Road widening
23 sq mland set aside for road widening

Timeline

RERA approvedDec 2017
Proposed completionDec 2023
TodayJul 2026
Construction progress

100% overall, as filed

Excavation100%
Basement & plinth100%
Podiums100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

21 of 21 available
BuildingFloorTypeArea sq mAvailable
KUSHAL SAI BUILDERS12BHK884 of 4
KUSHAL SAI BUILDERS22BHKmortgaged291 of 1
KUSHAL SAI BUILDERS22BHK591 of 1
KUSHAL SAI BUILDERS22BHKmortgaged882 of 2
KUSHAL SAI BUILDERS22BHK881 of 1
KUSHAL SAI BUILDERS32BHK884 of 4
KUSHAL SAI BUILDERS42BHK884 of 4
KUSHAL SAI BUILDERS52BHK884 of 4

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

KUSHALSAI BUILDERS AND DEVELOPERS

PartnershipPromoter type
Ranga Reddy, TelanganaBased in
2Projects
2Cities
2017–2024Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
37 homeson the public record across 2 projects
3,164 sq mbuilt-up filed
1,349 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

RERA Telangana · Registration filing
Locality
KAMALANAGAR
Mandal
Hayathnagar
District
Ranga Reddy
Pincode
500070
North boundary
30 FEET WIDE ROAD
East boundary
PARK
South boundary
PLOT NO 99 AND PLOT NO 98
West boundary
25 FEET WIDE ROAD
What’s nearby
Schools2 schools within 500m · 5 educational institutions within 1km · College or university 1.2km away
HealthcareHospital 249m away · 5 clinics within 1km · Pharmacy within 500m
LifestylePark 989m away · Gym or sports centre 161m away · 12+ restaurants and cafes within 1km
ShoppingSupermarket 128m away · Mall 1.8km away · Convenience store within 1km
Getting around
Expressway 806 m · Vijaywada HighwayPrimary road 1.9 km · Hyderabad - Nagarjuna Sagar RoadMetro station 3.8km away (L. B. Nagar Metro Station)Bus stop within 500m
Water & environment
Water body 1.8 km · Kappala Cheruvu
distances only — not a flood assessment
Declared external development
Roads100%
Water supply100%
Sewerage (Chamber,…100%
Rainwater100%
Green Strip/TOT LO…100%
Street lighting100%
Sewage100%
Rainwater100%
Fire safety100%
Electricity100%
Aggregate area of …100%
Community Building…0%
Solid waste0%
Renewable energy0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
04

Planning authority

RERA Telangana · Approved building plan

Greater Hyderabad Municipal Corporation (GHMC)

Municipal / Corporation
Building Permit no. 1/C23/12847/2017Survey no. 58/A

The promised possession date (19 Dec 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan 1/C23/12847/2017 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

GHMC

Municipal Corporation · Hyderabad city core

Has approved 3,102 RERA projectsabout 1 in 4 in Telangana.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
1,994
On record
2,20,211 flats · 3,387 plots
Reach
65 mandals
Since
2016

More apartment-heavy than Telangana overall — 99% apartments here vs 66% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.