Complete project overview

MahaRERA · Registration filing
Floors
4
Buildings
7
Parking
212 spaces
Land area
2,91,350 sq m
Sanctioned built-up
7,520 sq m
Recreational open space
48,725 sq m

Timeline

RERA registeredNov 2017
Proposed completionDec 2026
TodayJul 2026
Construction progress
Club10%
Sewerage (Chamber,…20%
Water conservation…30%
Aggregate area of …30%
Wellness centre30%
Landscaping & Tree…40%
Street Lighting40%
Electrical meter r…40%
Storm Water Drains50%
Internal Roads & F…70%
Water Supply70%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Mandke and Mandke Infrastructure Pvt. Ltd.

CompanyPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2017–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Asgoli
Taluka
Guhagar
District
Ratnagiri
Pincode
415703
Survey no.
Gat no. 813,Gat no. 814,Gat no. 815,Gat no. 816
North boundary
Gat No 819
East boundary
Village Road
South boundary
Palshet gaon
West boundary
Gat No 785
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.6 km · Chiplun Guhagar RoadPrimary road 2.0 kmNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 1.4 kmWater body 1.9 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Ratnagiri Collector

Collector office
Building Permit
Survey no. Gat no. 813,Gat no. 814,Gat no. 815,Gat no. 816
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.