Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
2
Parking
2 spaces
Land area
513 sq m
Sanctioned built-up
1,523 sq m

Timeline

RERA registeredSep 2023
Proposed completionJun 2025
TodayJul 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply50%
Solid Waste Manage…50%
Flat fit-out90%
OC-readiness95%
Fire protection an…95%
Excavation100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
External finishes100%
Storm Water Drains100%
Water conservation…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

OM CONSTRUCTION

CompanyPromoter type
Mumbai Suburban, MAHARASHTRABased in
20Projects
9Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
362 homeson the public record across 20 projects
25,333 sq mbuilt-up filed
8,267 sq mland declared
₹153.67 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Burdwan MunicipalityMunicipality1 of 7 projects
Gadhinglaj Municipal CouncilMunicipal Council1 of 7 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 7 projects
Kolkata Municipal CorporationMunicipal Corporation1 of 7 projects
Municipal Corporation of Greater MumbaiMunicipal Corporationthis project1 of 7 projects
North Barrackpore MunicipalityMunicipality1 of 7 projects
Others1 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Eksar
Taluka
Borivali
District
Mumbai Suburban
Pincode
400103
Survey no.
541D, 540C, 544
North boundary
EXISTING ROAD
East boundary
CTS 660B 1 A
South boundary
CTS 542 CTS 545
West boundary
CTS 536
What’s nearby
Schools2 schools within 1km · 3 educational institutions within 1km · College or university 1.7km away
HealthcareHospital 269m away · 14 clinics within 1km · Pharmacy within 500m
LifestylePark 1.2km away · Gym or sports centre 543m away · 13+ restaurants and cafes within 1km
ShoppingSupermarket 170m away · Mall 1.3km away · Bank 50m away
Getting around
Expressway 1.2 km · Western Express HighwayPrimary road 13 m · Devidas RoadRailway line 630 m · Western Railway Virar to BorivaliMetro station 959m away (Eksar)2 bus stops within 500m
Water & environment
River 583 m · Dahisar River
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Municipal Corporation of Greater Mumbai

Municipal Corporation · MCGM
Building Permit
Survey no. 541D, 540C, 544

The promised possession date (30 Jun 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation of Greater Mumbai

Municipal corporation

Has approved 2,862 RERA projectsabout 1 in 7 in Maharashtra, more than any other body in the state.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
2,166
On record
34,498 flats · 0 plots
Reach
9 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
Litigation3 cases on record, earliest 2022
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.