HORIZONMarkets
01

Complete project overview

JHARERA · Registration filing
Units
36 units
Carpet area
81–95 sq mper unit, as filed
Parking
20 spaces0 covered · 20 open
Amenities declared
Road · Drinking water · Water supply · Sewage & drainage · Electricity · Fire fighting · Emergency evacuation · Solid waste

Timeline

Building permit grantedJul 2020
Proposed completionJul 2023
TodayJul 2026

Find your flat

Every flat the builder registered, with the carpet area they filed. Look yours up and check it against what you were shown.

UnitCarpet sq m
1189.80
2189.80
3189.80
4181.20
5191.60
6194.70
7193.20
1289.80
2289.80
3289.80
4281.20
5291.60
6294.70
7293.20
1389.80
2389.80
3389.80
4381.20
5391.60
6394.70
7393.20
1489.80
2489.80
3489.80
4481.20
5491.60
6494.70
7493.20
1589.80
2589.80
3589.80
3589.80
4581.20
5591.60
6594.70
7593.20

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. Carpet area is the legally meaningful number — not the super built-up figure a brochure quotes.

02

Builder’s track record

JHARERA · Promoter registration

OM CONSTRUCTION

Partnership / LLPPromoter constitution
20Projects
9Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
362 homeson the public record across 20 projects
25,333 sq mbuilt-up filed
8,267 sq mland declared
₹153.67 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Burdwan MunicipalityMunicipality1 of 7 projects
Gadhinglaj Municipal CouncilMunicipal Council1 of 7 projects
Kalyan Dombivli Municipal CorporationMunicipal Corporation1 of 7 projects
Kolkata Municipal CorporationMunicipal Corporation1 of 7 projects
Municipal Corporation of Greater MumbaiMunicipal Corporation1 of 7 projects
North Barrackpore MunicipalityMunicipality1 of 7 projects
Others1 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

JHARERA · Registration filing
Address
SABALPUR,
What’s nearby
SchoolsNearest school 1.2km away
HealthcareHospital 1.1km away · Clinic within 2km · Pharmacy within 500m
LifestyleNo parks within 2km · Gym or sports centre 406m away
ShoppingNo supermarket within 2km · Mall 790m away · Bank 763m away
Getting around
Expressway 437 mPrimary road 641 m · Bhuiphore Hirak RoadNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
Water body 1.4 km · Subalpur PondRiver 3.1 km
distances only — not a flood assessment
04

Planning authority

JHARERA · Approved building plan
Building Permitapproved 16 Jul 2020 · 6 yrs ago

The promised possession date (16 Jul 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — JHARERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — JHARERA does not publish a complaints register. This read cannot speak to them either way.