Complete project overview

MahaRERA · Registration filing
Floors
14
Buildings
4
Parking
57 spaces
Land area
2,140 sq m
Sanctioned built-up
7,682 sq m

Timeline

RERA registeredAug 2018
Proposed completionMar 2022
TodayJul 2026
Construction progress
Podiums0%
Superstructure0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …10%
Open Parking50%
Internal Roads & F…90%
Water Supply90%
Sewerage (Chamber,…90%
Storm Water Drains90%
Landscaping & Tree…90%
Street Lighting90%
Community Building…90%
Excavation100%
Basement (if any)100%
Plinth100%
Stilt floor100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

MORAJ INFRATECH PRIVATE LIMITED

CompanyPromoter type
Thane, MAHARASHTRABased in
3Projects
3Cities
2017–2022Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
115 homeson the public record across 3 projects
14,841 sq mbuilt-up filed
7,261 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Khapari
Taluka
Nagpur (Rural)
District
Nagpur
Pincode
441108
Survey no.
PLOT NO. 5
North boundary
ROAD
East boundary
PROPOSED DEVELOPMENT
South boundary
PROPOSED COMMERCIAL DEVELOPMENT
West boundary
ROAD AND WATER CHANNEL
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.1km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 1.6 kmRailway line 900 m · Mumbai–Nagpur lineRailway station 1.6km away (Khapri)Limited bus connectivity nearby
Water & environment
River 1.5 kmWater body 4.4 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Maharashtra Airport Development Company Limited (Madc)

Building Permit
Survey no. PLOT NO. 5

The promised possession date (30 Mar 2022) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.