Complete project overview

MahaRERA · Registration filing
Floors
16
Buildings
2
Parking
144 spaces
Land area
3,669 sq m
Sanctioned built-up
13,766 sq m
Recreational open space
1,566 sq m

Timeline

RERA registeredMay 2022
Proposed completionMay 2027
TodayJul 2026
Construction progress
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Superstructure100%
Internal finishes100%
Flat fit-out100%
Stairs & lifts100%
External finishes100%
OC-readiness100%
Water Supply100%
Sewerage (Chamber,…100%
Landscaping & Tree…100%
Water conservation…100%
Fire protection an…100%
Electrical meter r…100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Neelkanth Infracon

PartnershipPromoter type
Thane, MAHARASHTRABased in
4Projects
3Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
157 homeson the public record across 4 projects
27,774 sq mbuilt-up filed
9,301 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 2 projects
Panvel Municipal CorporationMunicipal Corporation1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Khanda Colony
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
plot_no 35 city_survey_gut_no - final_plot_no - sector_no 17 mauje NEW PANVEL WEST road_street - society -
North boundary
Plot no 33 34 34A
East boundary
20 Mtr wide road
South boundary
20 Mtr wide road
West boundary
Plot no 36
What’s nearby
Schools1 school within 1km
HealthcareHospital 164m away · 1 clinic within 1km
LifestylePark 862m away · Gym or sports centre 419m away · 8 restaurants and cafes within 1km
ShoppingSupermarket 422m away · Bank 415m away
Getting around
Expressway 1.7 kmPrimary road 1.2 kmRailway line 458 m · Harbour LineRailway station 716m away (Mansarovar)Limited bus connectivity nearby
Water & environment
Water body 189 mRiver 1.3 km · Kalundre River
distances only — not a flood assessment
Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.