HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
17
Buildings
2
Parking
139 spaces
Land area
3,882 sq m
Sanctioned built-up
5,819 sq m

Timeline

RERA registeredFeb 2024
Proposed completionDec 2028
TodayJul 2026
Construction progress
Flat fit-out0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
Aggregate area of …0%
External finishes15%
Internal finishes65%
Stairs & lifts75%
Superstructure90%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Stilt floor100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Neelkanth Infracon

PartnershipPromoter type
Thane, MAHARASHTRABased in
4Projects
3Cities
2019–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
157 homeson the public record across 4 projects
27,774 sq mbuilt-up filed
9,301 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 2 projects
Panvel Municipal CorporationMunicipal Corporationthis project1 of 2 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Khanda Colony
Taluka
Panvel
District
Raigarh
Pincode
410206
Survey no.
Plot No 36, Sector 17
North boundary
Plot No 32
East boundary
Plot No 35
South boundary
20 m wide existing road
West boundary
Plot No 37
What’s nearby
Schools1 school within 1km
HealthcareHospital 501m away · 1 clinic within 1km
LifestylePark 1.7km away
ShoppingSupermarket 228m away
Getting around
Expressway 149 mPrimary road 556 mRailway line 293 m · Harbour LineRailway station 1.2km away (Khandeshwar)3 bus stops within 500m
Water & environment
Water body 478 m
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Panvel Municipal Corporation

Municipal Corporation
Building Permit
Survey no. Plot No 36, Sector 17
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Panvel Municipal Corporation

Municipal corporation

Has approved 305 RERA projects1.5% of Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
238
On record
4,602 flats · 0 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
EncumbranceDeclared financial encumbrance on the project
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.