Complete project overview

MahaRERA · Registration filing
Plots
58 plots
Land area
36,000 sq m
Recreational open space
3,600 sq m

Timeline

RERA registeredMay 2026
Proposed completionDec 2027
TodayJul 2026
Construction progress
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Energy managemcnt0%
Electrical meter r…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

Shahaji Sakharam Sawant

IndividualPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2026–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this promoter so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Theur
Taluka
Haveli
District
Pune
Pincode
412110
Survey no.
Gat No. 168(P)
North boundary
Gat No 169
East boundary
Internal 12 Meter Road
South boundary
Remaining Area of Gat No 168
West boundary
Remaining Area of Gat No 168
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 4.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 368 mRailway line 3.3 km · Pune - Daund Railway LineRailway station 4.6km away (Loni)Limited bus connectivity nearby
Water & environment
River 825 m · Mula-MuthaWater body 3.4 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Pune Metropolitan Region Development Authority

Metropolitan Development Authority
Layout Permit
Survey no. Gat No. 168(P)
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Pune Metropolitan Region Development Authority

Metropolitan / development authority

Has approved 1,013 RERA projectsabout 1 in 20 in Maharashtra.

an apartments market87% apartments · 13% plotted layouts. Layouts like yours are the smaller share here — this body mostly approves apartments.

Builders
604
On record
21,940 flats · 10,299 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.