Complete project overview

UP-RERA · Registration filing
Units
108 units
Unit mix
108 × 2 BHK
Carpet area
65 sq mper unit, as filed
Floors
9
Blocks
3
Land area
2,720 sq m

Timeline

Project startedDec 2012
RERA registeredJul 2017
Proposed completionOct 2020
TodayJul 2026

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

108 units across 27 batches
BuildingFloorTypeArea sq mCount
TOWER 1012 BHK654
TOWER 1022 BHK654
TOWER 1032 BHK654
TOWER 1042 BHK654
TOWER 1052 BHK654
TOWER 1062 BHK654
TOWER 1072 BHK654
TOWER 1082 BHK654
TOWER 1092 BHK654
TOWER 612 BHK654
TOWER 622 BHK654
TOWER 632 BHK654
TOWER 642 BHK654
TOWER 652 BHK654
TOWER 662 BHK654
TOWER 672 BHK654
TOWER 682 BHK654
TOWER 692 BHK654
TOWER 812 BHK654
TOWER 822 BHK654
TOWER 832 BHK654
TOWER 842 BHK654
TOWER 852 BHK654
TOWER 862 BHK654
TOWER 872 BHK654
TOWER 882 BHK654
TOWER 892 BHK654

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

UP-RERA · Promoter registration

PARSVNATH DEVELOPERS LIMITED

CompanyPromoter type
18Registered projects
25Projects
8Cities
2017–2025Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
2,490 homes · 1,621 plotson the public record across 25 projects
13,602 sq mbuilt-up filed
1,55,352 sq mplotted area
4,10,520 sq mland declared
₹1299.81 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
SanwerTown & Country Planning (DTCP)4 of 7 projects
Saharanpur Development AuthorityDevelopment Authority3 of 7 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

UP-RERA · Registration filing
District
Moradabad
Tehsil
Moradabad
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 1.3km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 326 mPrimary road 372 mNo metro or railway within 5kmLimited bus connectivity nearby
Water & environment
River 1.7 km · Gangan
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹24.13 Cr declared to build 108 flats. What that works out to:

₹22.34 Lakhdeclared cost per flatall-in — land + construction

This is what the promoter filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Planning authority

UP-RERA · Approved building plan
approved 11 Aug 2014 · 11 yrs ago
Building Permit no. BF/MH/VC/151(06-07)14-15

The promised possession date (31 Oct 2020) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BF/MH/VC/151(06-07)14-15 on the approving authority’s portal to confirm the sanction.

Complaints register

3 complaints on UP-RERA’s register for this project.

A count from the authority’s public register — not a judgement. A disposed complaint may have been resolved for or against the builder, and only disputes escalated this far appear at all.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — UP-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.