HORIZONMarkets
01

Complete project overview

RERA Telangana · Registration filing
Units
15 units
Unit mix
15 × 2BHK
Saleable area
109–121 sq mper unit, as filed
Floors
5
Land area
583 sq m
Built-up area
1,320 sq m

Timeline

RERA approvedJul 2018
Proposed completionJul 2024
TodayJul 2026
Construction progress

21% overall, as filed

Basement & plinth0%
Podiums0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Superstructure50%
Excavation80%
Stilt floor80%
Per-stage % as filed with the authority — a snapshot, not a live tracker. The lowest figure across every building/block, so no stage reads further along than the project’s slowest block.

Find your flat

Filed by floor and type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

15 of 15 available
BuildingFloorTypeArea sq mAvailable
PRANAVAM12BHKmortgaged1211 of 1
PRANAVAM12BHK1091 of 1
PRANAVAM12BHKmortgaged1111 of 1
PRANAVAM22BHK1112 of 2
PRANAVAM22BHK1091 of 1
PRANAVAM32BHK1091 of 1
PRANAVAM32BHK1111 of 1
PRANAVAM32BHK1211 of 1
PRANAVAM42BHK1091 of 1
PRANAVAM42BHK1111 of 1
PRANAVAM42BHK1211 of 1
PRANAVAM52BHK1091 of 1
PRANAVAM52BHK1111 of 1
PRANAVAM52BHK1211 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system. "Mortgaged" batches were declared under mortgage to a bank/lender for project finance — check with the promoter that any specific flat is released before relying on clear title.

02

Builder’s track record

RERA Telangana · Promoter registration

Aditya Developers

PartnershipPromoter type
Medchal-Malkajgiri, TelanganaBased in
30Projects
14Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,403 homes · 172 plotson the public record across 30 projects
93,665 sq mbuilt-up filed
10,136 sq mplotted area
65,460 sq mland declared
₹133.89 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Greater Hyderabad Municipal Corporation (GHMC)Municipal / Corporation4 of 18 projects
Ahmedabad Municipal CorporationMunicipal / Corporation2 of 18 projects
IndoreTown & Country Planning (DTCP)2 of 18 projects
Others2 of 18 projects
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 18 projects
Bhavnagar Municipal CorporationMunicipal / Corporation1 of 18 projects
Gandhinagar Municipal CorporationMunicipal / Corporation1 of 18 projects
Nagpur Metropolitan Region Development AuthorityMetropolitan Development Authority1 of 18 projects
Nashik Municipal CorporationMunicipal Corporation1 of 18 projects
Surat Municipal CorporationMunicipal / Corporation1 of 18 projects
Talegaon Dabhade Municipal CouncilMunicipal Council1 of 18 projects
Vadodara Urban Development AuthorityUrban Development Authority1 of 18 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location & price analysis

RERA Telangana · Registration filing
Locality
NALLAGANDLA
Village
Nallagandla
Mandal
Serilingampally
District
Ranga Reddy
Pincode
500019
North boundary
ROAD
East boundary
PLOT NO 200
South boundary
HCU LAND
West boundary
PLOT NO 203
What’s nearby
Schools3 schools within 1km · 11 educational institutions within 1km · College or university 460m away
HealthcareHospital 458m away · Clinic within 2km · Pharmacy within 500m
LifestylePark 1.7km away · Gym or sports centre 127m away
ShoppingSupermarket 135m away · Bank 978m away · ATM within 500m
Getting around
Expressway 2.4 km · Chandanagar - RC Puram BHEL Rd Mumbai HighwayPrimary road 599 m · Nallagandla FlyoverRailway line 698 mRailway station 1.2km away (Lingampalli)Limited bus connectivity nearby
Water & environment
Water body 1.5 km · Irrigation Pond
distances only — not a flood assessment
Government land classification

No residential (House Sites) class on record. The state classes this village’s land as Dry land. If it’s sold as residential plots, verify the layout’s conversion / approval.

Telangana Registration & Stamps
Declared external development
Roads0%
Water supply0%
Sewerage (Chamber,…0%
Rainwater0%
Green Strip/TOT LO…0%
Street lighting0%
Community Building…0%
Sewage0%
Solid waste0%
Rainwater0%
Renewable energy0%
Fire safety0%
Electricity0%
Aggregate area of …0%
% complete as filed at registration — no progress updates are published, so this is a starting-line snapshot.
Price analysisno declared cost on this filing — one government benchmark below

This state’s RERA filing carries no declared build cost at all — nothing to turn into a per-unit or per-sq-ft figure here. The one real, government-sourced number below is the closest thing to a benchmark this record can offer.

Government guidance value
₹33,100/sq ydresidential

₹39,587/sq m · effective May 2026 · apartments ₹3,000/sq ft, same source

The state’s minimum value for this locality’s land, set for stamp duty — a floor, not a market price. Source: Telangana Registration & Stamps.

04

Planning authority

RERA Telangana · Approved building plan
Building Permit
Survey no. 10,11,12

The promised possession date (7 Jul 2024) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RERA Telangana does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RERA Telangana does not publish a complaints register. This read cannot speak to them either way.