HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
7
Buildings
2
Land area
570 sq m
Sanctioned built-up
1,914 sq m

Timeline

RERA registeredOct 2023
Proposed completionAug 2026
TodayJul 2026
02

Builder’s track record

MahaRERA · Promoter registration

BALAJI DEVELOPERS

PartnershipPromoter type
Kolhapur, MAHARASHTRABased in
45Projects
27Cities
2017–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
1,705 homes · 1,332 plotson the public record across 45 projects
94,749 sq mbuilt-up filed
71,649 sq mplotted area
1,78,134 sq mland declared
₹259.44 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Rajkot Municipal CorporationMunicipal / Corporation4 of 31 projects
KhargoneTown & Country Planning (DTCP)3 of 31 projects
DewasTown & Country Planning (DTCP)2 of 31 projects
Jaipur Development AuthorityDevelopment Authority2 of 31 projects
Others2 of 31 projects
Ahmedabad Municipal CorporationMunicipal / Corporation1 of 31 projects
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 31 projects
CMDA (Chennai Metropolitan Development Authority)CMDA (Chennai Metropolitan Development Authority)1 of 31 projects
Gandhinagar Urban Development AuthorityUrban Development Authority1 of 31 projects
Gram PanchayatGram Panchayat1 of 31 projects
Hyderabad Metropolitan Development Authority (HMDA)Urban Development Authority1 of 31 projects
Jaysingpur Minicipal Council Jaysingpurthis project1 of 31 projects
Kulgaon Badlapur Nagar ParishadMunicipal Council1 of 31 projects
Nashik Municipal CorporationMunicipal Corporation1 of 31 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 31 projects
Pune Metropolitan Region Development AuthorityMetropolitan Development Authority1 of 31 projects
Pune Municipal CorporationMunicipal Corporation1 of 31 projects
Surat Urban Development AuthorityUrban Development Authority1 of 31 projects
The Office Of Sub Division Town Planning Raigad1 of 31 projects
Umargam MunicipalityMunicipal / Corporation1 of 31 projects
Urban Improvement TrustUrban Improvement Trust1 of 31 projects
Vadodara Municipal CorporationMunicipal / Corporation1 of 31 projects
Vice Chairman, UDAUrban Development Authority1 of 31 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
jaysingpur
Taluka
Shirol
District
Kolhapur
Pincode
416101
Survey no.
101/2/B/22
North boundary
18M WIDE ROAD
East boundary
S NO 101-3
South boundary
S NO 101-2-B-23
West boundary
9M IWIDE ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 3.0km away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 82 m · Kolhapur-Miraj RoadPrimary road 3.0 km · ichalkaranji Sangli RoadRailway line 2.7 kmRailway station 3.7km away (Jayasingpur)Limited bus connectivity nearby
Water & environment
Water body 1.9 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Jaysingpur Minicipal Council Jaysingpur

Building Permit
Survey no. 101/2/B/22
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that sanctioned this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.