HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
32 units
Mix
32 × 3BHK
Booked
21 of 32 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
1,729 sq m
Floor area
7,374 sq m
Description
RDS ZEAL

Timeline

Project startedDec 2022
RERA registeredDec 2022
Proposed completionDec 2026
TodayJul 2026
Construction progress

25% overall, as filed

Sanitary Fittings0%
Electrical Fittings0%
Overhead and Underground Water Tanks.0%
The external plumbing and external plastering0%
Completion of terraces floor each building0%
Installation of lifts, water pumps etc0%
Fire Fighting Fittings and Equipment0%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc0%
Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings8%
Staircases, Lifts Wells75%
Slabs of Super Structure90%
Excavation100%
Basement(s) and Plinth100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

11 of 32 available
TypeArea sq mAvailable
3BHK1330 of 10
3BHK1325 of 11
3BHK1236 of 11

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

RDS REALTIES LTD

CompanyPromoter type
Ernakulam, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
3Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
107 homeson the public record across 3 projects
20,510 sq mbuilt-up filed
5,736 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
MANIMALA ROAD
Village
EDAPPALLY NORTH
Taluk
Kanayannur
District
Ernakulam
Pincode
682024
Survey no.
20
Patta no.
11844
What’s nearby
Schools4 schools within 1km · 5 educational institutions within 1km · College or university 732m away
HealthcareHospital 569m away · 5 clinics within 1km · Pharmacy within 500m
LifestylePark 961m away · Gym or sports centre 342m away · 45+ restaurants and cafes within 1km
ShoppingSupermarket 385m away · Mall 598m away · Convenience store within 1km
Getting around
Expressway 447 mPrimary road 455 m · Old National Highway 17Railway line 1.2 kmMetro station 583m away (Edappally)4 bus stops within 500m
Water & environment
Water body 392 m · Chenankulangara temple pondCanal 636 m · Chithrapuzha
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Cochin Municipal Corporation

Municipal Corporation
approved 22 Nov 2022 · 3 yrs ago
Building Permit no. EYP3/283/COC/EYP/2091/19Survey no. 20
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan EYP3/283/COC/EYP/2091/19 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Cochin Municipal Corporation

Municipal corporation / municipality

Has approved 40 RERA projects2.6% of Kerala.

an apartments market98% apartments · 2% plotted layouts. Apartments like yours are this body's core business.

Builders
24
On record
1,429 flats · 19 plots
Since
2021

More apartment-heavy than Kerala overall — 98% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.