HORIZONMarkets
01

Complete project overview

K-RERA · Registration filing
Units
27 units
Mix
19 × 2BHK · 4 × 1BHK · 3 × 3BHK · 1 × 2BHK with Study
Booked
27 of 27 filed sold/bookedas declared in the RERA filing
Buildings
1
Land area
910 sq m
Floor area
2,707 sq m
Description
REIGATE SERENITY

Timeline

Project startedFeb 2021
RERA registeredMar 2021
Proposed completionJul 2023
TodayJul 2026
Construction progress

88% overall, as filed

Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0%
Overall Percentage of Completion of the work done For the entire Building /Wing0%
Excavation100%
Basement(s) and Plinth100%
Stilt Floor100%
Slabs of Super Structure100%
Internal walls, Internal Plastering, Floorings inside the building, Doors and Windows to each Buildings100%
Sanitary Fittings100%
Electrical Fittings100%
Staircases, Lifts Wells100%
Overhead and Underground Water Tanks.100%
The external plumbing and external plastering100%
Completion of terraces floor each building100%
Installation of lifts, water pumps etc100%
Fire Fighting Fittings and Equipment100%
Common Areas work for each building like electrical fittings and other finishing works such as paving of common area etc100%
Per-activity completion % from the promoter's construction-task checklist filed with K-RERA — overall is the average across activities, as of that filing. A dated snapshot, not a live tracker.

Find your flat

Filed by type and size, in the batches the promoter registered — not a per-flat listing. Look yours up.

0 of 27 available
TypeArea sq mAvailable
3BHK850 of 2
3BHK830 of 1
1BHK450 of 2
1BHK450 of 1
1BHK430 of 1
2BHK580 of 3
2BHK570 of 1
2BHK710 of 4
2BHK710 of 1
2BHK540 of 1
2BHK630 of 1
2BHK590 of 1
2BHK550 of 2
2BHK630 of 3
2BHK530 of 1
2BHK with Study790 of 1
2BHK540 of 1

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. As filed at registration, in the batches the promoter declared — not a live booking system.

02

Builder’s track record

K-RERA · Promoter registration

REIGATE BUILDERS PRIVATE LIMITED

CompanyPromoter type
Kozhikode, KeralaBased in
Yes — the promoter declared prior project experienceDeclared prior experience
5Projects
1Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
265 homeson the public record across 5 projects
36,164 sq mbuilt-up filed
8,447 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Kozhikode Municipal CorporationMunicipal Corporationthis project4 of 5 projects
Municipal Corporation KozhikodeLocal body (LSGI)1 of 5 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

K-RERA · Registration filing
Street
CHEVAYUR
Village
CHEVAYUR
Taluk
Kozhikode
District
Kozhikode
Pincode
673008
Survey no.
321/1, 321/23, 321/24
Patta no.
18469
What’s nearby
Schools2 schools within 500m · 6 educational institutions within 1km · College or university 1.0km away
HealthcareHospital 252m away · 1 clinic within 1km · Pharmacy within 1km
LifestylePark 1.1km away · 7 restaurants and cafes within 1km
ShoppingSupermarket 439m away · Mall 1.2km away · Convenience store within 1km
Getting around
Expressway 1.1 km · Kannur-Calicut-Valanchery HighwayPrimary road 1.3 km · Mayanad Bypass RoadNo metro or railway within 5km5 bus stops within 500m
Water & environment
Water body 652 m
distances only — not a flood assessment
04

Planning authority

K-RERA · Approved building plan

Kozhikode Municipal Corporation

Municipal Corporation
approved 10 Jul 2020 · 6 yrs ago
Building Permit no. BPA72020004161Survey no. 321/1, 321/23, 321/24

The promised possession date (6 Jul 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

Verify it yourself — look up plan BPA72020004161 on the approving authority’s portal to confirm the sanction.

The approving body, at scale

Kozhikode Municipal Corporation

Municipal corporation / municipality

Has approved 57 RERA projects3.7% of Kerala.

an apartments market96% apartments · 4% plotted layouts. Apartments like yours are this body's core business.

Builders
36
On record
3,822 flats · 80 plots
Since
2021

More apartment-heavy than Kerala overall — 96% apartments here vs 81% statewide.

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — K-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — K-RERA does not publish a complaints register. This read cannot speak to them either way.