HORIZONMarkets
01

Complete project overview

MahaRERA · Registration filing
Floors
6
Buildings
4
Land area
2,454 sq m
Sanctioned built-up
7,782 sq m

Timeline

RERA registeredJan 2023
Proposed completionDec 2027
TodayJul 2026
Construction progress
Stilt floor0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Community Building…0%
Water conservation…0%
Fire protection an…0%
Electrical meter r…0%
OC-readiness60%
Internal finishes95%
Flat fit-out95%
Stairs & lifts95%
External finishes95%
Excavation100%
Basement (if any)100%
Podiums100%
Plinth100%
Superstructure100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

DEV DEVELOPERS

PartnershipPromoter type
Nashik, MAHARASHTRABased in
12Projects
7Cities
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
528 homeson the public record across 12 projects
36,457 sq mbuilt-up filed
47,007 sq mland declared
₹190.63 Crdeclared build cost

Build cost is what the promoter declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Municipal CorporationMunicipal / Corporation3 of 12 projects
Others3 of 12 projects
Rajkot Municipal CorporationMunicipal / Corporation2 of 12 projects
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 12 projects
Anand VallabhVidhyanagar Karmsad Urban Development AuthorityUrban Development Authority1 of 12 projects
Badlapur Municipal1 of 12 projects
Nashik Municipal CorporationMunicipal Corporationthis project1 of 12 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Deolaligaon
Taluka
Nashik
District
Nashik
Pincode
422101
Survey no.
PLOT NO 1+2+3/1 S NO 114/A1/1+114A/3+114/C
North boundary
12 METER WIDE ROAD
East boundary
PLOT NO 4 5
South boundary
PLOT NO 1-2-3-2
West boundary
12 METER WIDE ROAD
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 54m away
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 4.2 km · Pune Nashik RoadPrimary road 3.4 kmRailway line 411 mRailway station 1.2km away (Devlali)Limited bus connectivity nearby
Water & environment
River 1.0 km · Darna
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Nashik Municipal Corporation

Municipal Corporation
Building Permit
Survey no. PLOT NO 1+2+3/1 S NO 114/A1/1+114A/3+114/C
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Nashik Municipal Corporation

Municipal corporation

Has approved 821 RERA projectsabout 1 in 24 in Maharashtra.

an apartments market100% apartments · 0% plotted layouts. Apartments like yours are this body's core business.

Builders
692
On record
4,331 flats · 111 plots
Reach
2 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.