Complete project overview

RAJ-RERA · Registration filing
Plots
98 plots
Land area
15,881 sq m
Completion deadline extended
2 extensions on record — latest to 31 Dec 2024declared reason: other than force majeure
Description
1. According to Rajasthan Township Policy - 2010, Plot No. : A12, A13, A14, A15, A16, C16, C17, C22, C24, D7, D8, D16, D17, D24 Each Size 20*50 and one informal sector = Total : 14 Plots and 1 Informal Sectors have been mortgaged with UIT. 2. As per Plot Release Letter Dated :- 28-03-2022 – Plot No. :- A-12, D-07, D-08 Each Size 20'-0" X 50'-0" Feet Total 03 Plot are now released; AND Plot Nos. :- A-13 to A-16, C-16, C-17, C-22, C-24, D-16, D-17, D-24 Each Size 20'-0" X 50'-0" Feet Informal Sector Size 42'-9" X 80'-0" Feet Total 11 Plot & 01 Informal Sector are still mortgaged till further Orders. 3. As per the Plot Release Letter Dated :- 10-03-2023 – Plot No. :- A-13, A-14, A-15, A-16, Each Size 20'-0" X 50'-0" Feet, Total 04 Plots are now released; AND Plot Nos. :- C-16, C-17, C-22, C-24, D-16, D-17, D-24 Each Size 20'-0" X 50'-0" Feet Informal Sector Size 42'-9" X 80'-0" Feet Total 07 Plot & 01 Informal are still mortgaged till further orders. 4. As per the Plot Release Letter Dated :- 04-10-2024 – Plot No. :- C-16, C-17, C-22, C-24, D-16, D-17, D-24 Each Size 20'-0" X 50'-0" Feet, Total 07 Plots are now released; AND Plot Informal Sector Size 42'-9" X 80'-0" Feet Total 01 Informal Sector is still mortgaged till further orders. 5. As per the Final Plot Release Letter Dated :- 24-12-2024 – Informal Sector Size 42'-9" X 80'-0" Feet Total 01 Informal Sector is now released.

Timeline

Construction startNov 2021
RERA registeredJan 2022
Proposed completionOct 2023
TodaySep 2026

Find your plot

Filed by type and size, in the batches the builder registered — not a per-plot listing. Look yours up.

98 plots across 9 batches
TypeArea sq mCount
Plot9320
Plot9124
Plot9320
Plot9319
Plot934
Plot935
Plot1391
Plot3181
Plot934

Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each size exist, not how many are still unsold (this state's filing carries no booking count).

02

Builder’s track record

RAJ-RERA · Builder registration

Suresh Shah

IndividualPromoter type
Sri Ganganagar, RajasthanBased in
11Projects
1City
2021–2026Active
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
519 plotson the public record across 11 projects
1,34,690 sq mplotted area
1,34,690 sq mland declared
₹23.92 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from Suresh Shah— the full portfolio →

03

Location & price analysis

RAJ-RERA · Registration filing
Address
Killa No. 7/2,14/2,17/2,24/2 and 08,13,18,23, Square No. 3, Chak 4 E Chhotti, Sri Ganganagar, Ganganagar, Sri Ganganagar, 335001
Village
Sri Ganganagar
Taluka
Ganganagar
District
Sri Ganganagar
Pincode
335001
What’s nearby
SchoolsNo schools within 2km
HealthcareNearest hospital 2.2km away · Clinic within 2km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 876 mPrimary road 1.2 kmRailway line 1.2 kmRailway station 4.3km away (Sriganganagar Junction)Limited bus connectivity nearby
Water & environment
Canal 379 mWater body 3.0 km
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹2.46 Cr declared to build 98 plots. What that works out to:

₹2.51 Lakhdeclared cost per plotall-in — land + construction
₹144/sq ftof plotted area₹1,551/sq m
74%of the cost is land₹107/sq ft of land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Rajasthan registration department

In Rajasthan it’s called the DLC rate.

No government guidance rate is shown for this project.

Rajasthan's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

RAJ-RERA · Approved building plan

Urban Improvement Trust

Urban Improvement Trust
Layout Permitapproved 15 Jan 2022 · 4 yrs ago

The promised possession date (31 Oct 2023) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

Urban Improvement Trust

A city-level Urban Improvement Trust — Rajasthan's town-development body in cities without a development authority. It has approved 612 RERA projects across 20 districts about 1 in 4 in Rajasthan.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by RAJ-RERA

07

Other projects nearby

The register · within 25 km

89 plotted projects still under way within 25 km. Step out ring by ring:

Of the 130 projects the radar draws within 6 km — every kind, every stage — 71 are plotted projects still under way. This list keeps only those, and looks further out.

11 projects within 1 km — showing the nearest 6.

190 m awayPlotted Development

DEVAKI ESTATES

SOHAN LAL · Ganganagar · Sri Ganganagar

Feb 2025registered
Jul 2026target completion
Declared cost₹3.00 CrScale20 plotsAuthorityRAJ-RERA
210 m awayPlotted Development

SHREE RADHEY BALAJI HOMES

SRE HOME DEVELOPERS PRIVATE LIMITED · Ganganagar · Sri Ganganagar

Jun 2025registered
Oct 2026target completion
Declared cost₹2.75 CrScale132 plotsAuthorityRAJ-RERA
380 m awayPlotted Development

Ridhi Sidhi Enclave 11

Abheet Singh Cheema · Ganganagar · Sri Ganganagar

Nov 2025registered
Sep 2026target completion
Declared cost₹2.79 CrScale83 plotsAuthorityRAJ-RERA
380 m awayPlotted Development

Ridhi Sidhi Enclave 11 Extension

Abheet Singh Cheema · Ganganagar · Sri Ganganagar

Nov 2025registered
Sep 2026target completion
Declared cost₹2.63 CrScale82 plotsAuthorityRAJ-RERA
430 m awayPlotted Development

RIDHI SIDHI COMMERCIAL HUB B BLOCK EXTENSION

MUKESH SHAH · Ganganagar · Sri Ganganagar

May 2025registered
Dec 2026target completion
possession revisedDeclared cost₹1.32 CrScale20 plotsAuthorityRAJ-RERA
440 m awayPlotted Development

RIDHI SIDHI COMMERCIAL HUB BLOCK A

Suresh Shah · Ganganagar · Sri Ganganagar

Apr 2025registered
Oct 2026target completion
possession revisedDeclared cost₹2.82 CrScale36 plotsAuthorityRAJ-RERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.
  • Construction progress — RAJ-RERA does not publish quarterly progress reports. How far along it actually is cannot be read here.
  • Complaints — RAJ-RERA does not publish a complaints register. This read cannot speak to them either way.