ROYAL RESIDENCY PHASE -I

PCGRERA060718000476 · RERA Chhattisgarh · https://gethorizon.in/projects/royal-residency-phase-i-durg-vf6tftyu

01

Complete project overview

RERA Chhattisgarh · Registration filing
Project name
ROYAL RESIDENCY PHASE -I
Quarterly reports
13 on filequarterly progress reports filed with RERA

Timeline

RERA registeredJul 2018
Proposed completionDec 2021
TodaySep 2026
Construction progress

100% overall, as filed

00%
Internal Roads And Footpaths100%
Water Supply100%
Sewerage100%
Storm Water Drains100%
Landscaping And Tree Planting100%
Street Lighting100%
Solid Waste Management And Disposal100%
Water Conservation Rain Water Harvesting100%
Energy Maanagement100%
Boundary Wall100%
Security Service100%
From the builder's latest quarterly progress report filed with RERA Chhattisgarh — % complete overall and per infrastructure work, as of that filing. A dated snapshot, not a live tracker.
02

Builder’s track record

RERA Chhattisgarh · Builder registration

SUYASH BUILDCON

Partnership FirmPromoter type
7Projects
1City
2018–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
360 plotson the public record across 7 projects
₹74.63 Crdeclared build cost

Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.

Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

More from SUYASH BUILDCON— the full portfolio →

03

Location & price analysis

RERA Chhattisgarh · Registration filing
District
Durg
Tehsil
Durg
Address
VILLAGE - POTIYAKALA, BORSI, DURG (C.G.)
What’s nearby
SchoolsNearest school 1.5km away
HealthcareHospital 824m away · 3 clinics within 1km
LifestylePark 1.4km away
ShoppingNo supermarket within 2km
Getting around
Expressway 4.1 kmPrimary road 2.8 km · Ravishankar ChowkRailway line 346 mRailway station 3.8km away (Durg Junction)Limited bus connectivity nearby
Water & environment
Water body 453 m
distances only — not a flood assessment
Price analysisdeclared build cost — not a sale price

₹8.32 Cr declared. What that works out to:

61%of the cost is land

This is what the builder filed it costs to build — land plus construction, at registration — not a sale price. The gap to an asking price is their margin, taxes and anything the filing doesn’t carry.

04

Government Guidance Rate

Chhattisgarh registration department

In Chhattisgarh it’s called the collector guideline rate.

No government guidance rate is shown for this project.

Chhattisgarh's government guidance rates aren't in Horizon's record yet.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

06

Other projects nearby

The register · within 25 km

50 plotted projects still under way within 25 km. Step out ring by ring:

Of the 109 projects the radar draws within 6 km — every kind, every stage — 19 are plotted projects still under way. This list keeps only those, and looks further out.

1 project within 1 km — showing the nearest 1.

760 m awayResidential Plotted Development

C.G. City ECO PHASE - II

S K A BUILDCON PVT. LTD. · Bhilai

May 2026registered
Apr 2031target completion
Declared cost₹8.28 CrScale28 plotsAuthorityRERA Chhattisgarh

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.