Filed by type and size, in the batches the builder registered — not a per-flat listing. Look yours up.
29 units across 10 batches
TypeArea sq mCount
1 BHK256
1 RK201
1 RK192
1 BHK276
1 BHK266
Shop121
Shop124
1 RK191
1 RK161
1 RK161
Shown in sq m. The filing records square metres; the sq-ft view is a straight conversion. The declared inventory as registered — how many of each type exist, not how many are still unsold (this state's filing carries no booking count).
Build cost is what the builder declared it costs to build — land plus construction, at registration. It gives a sense of how big a builder this is — not a price you pay, not build quality, and not whether they finish on time.
Every project Horizon has read from this builder, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.
Expressway 187 m · Panvel Flyover RampPrimary road 166 m · Uran RoadRailway line 388 m · Harbour LineRailway station 545m away (Panvel)2 bus stops within 500m
Water & environment
Water body 92 m
distances only — not a flood assessment
Location — done
04
Government Guidance Rate
Maharashtra IGR — Annual Statement of Rates
In Maharashtra it’s called the ready reckoner rate.
₹46,238per sq yd
₹55,300per sq m
Which rate
residential building or flat
Matched to
The rate published for the village of “Vadghar (CT)”.
In force
2026-2027 schedule
What this number is — and isn’t
The minimum value Maharashtra’s registration department will register a sale at. Stamp duty is usually charged on this or the price in the sale deed, whichever is higher.
Not a market price. Sales normally register above it, and how far above varies by place and by project.
Its fit depends on the grain the state publishes at. This one is matched at the level of village, and says so above. How Horizon decides what to show.
Government Guidance Rate — done
05
Complaints & litigation
MahaRERA · public record
Complaints register
None on record with MahaRERA against this project.
Only disputes escalated to the authority appear on the record — a private disagreement never filed here would not. A count from the public record, not a verdict.
What the builder declared
Declared to MahaRERA
Litigation
None declared to MahaRERA
The builder's own declaration at registration — not a court's or MahaRERA's finding. A flagged line is worth checking with MahaRERA.
Not a verdict. A complaint can be dismissed and a case can be won; an order can be appealed.
Not a clean bill. An empty record means nothing was filed with MahaRERA, or that this register doesn’t publish it — never that nothing happened.
Complaints & litigation — done
06
Other projects nearby
The register · within 25 km
2,466 residential projects still under way within 25 km. Step out ring by ring:
75 projects within 1 km — showing the nearest 6.
PanvelOthers
Manasi Smruti
M P Constructions
4 yr 11 mo
Apr 2022registered
Mar 2027target completion
Government Guidance Rate₹78,680/sq ydScale147 flatsAuthorityMahaRERA