SAI ICON

P52600054657 · MahaRERA · https://gethorizon.in/projects/sai-icon-murarji-peth-solapur-solapur-north-2abahpll

01

Complete project overview

MahaRERA · Registration filing
Units
71 units
Floors
5
Buildings
2
Parking
42 spaces
Land area
1,879 sq m
Sanctioned built-up
2,593 sq m

Timeline

RERA registeredFeb 2024
Proposed completionOct 2027
TodaySep 2026
Construction progress
Excavation0%
Basement (if any)0%
Podiums0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Internal Roads & F…0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Street Lighting0%
Treatment And Disp…0%
Solid Waste Manage…0%
Water conservation…0%
Energy managemcnt0%
Fire protection an…0%
Electrical meter r…0%
Open Parking0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

BJR CONTRUCTIONS PRIVATE LIMITED

CompanyPromoter type
Pune, MAHARASHTRABased in
1Projects
1City
2024–presentActive
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Taluka
Solapur North
District
Solapur
Pincode
413001
Survey no.
T.P.-4, F.P. NO 117, SUB PLOT NO 41
North boundary
Internal Road
East boundary
CTS 117 40
South boundary
Canal
West boundary
T P Road
What’s nearby
Schools2 schools within 1km · College or university 1.5km away
HealthcareHospital 392m away · 4 clinics within 1km
LifestylePark 1.3km away
ShoppingNo supermarket within 2km
Getting around
Expressway 772 mPrimary road 435 mRailway line 647 mRailway station 1.5km away (Solapur)Bus stop within 1km
Water & environment
Canal 1.9 km
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

Solapur Municipal Corportation

Building Permit
Survey no. T.P.-4, F.P. NO 117, SUB PLOT NO 41
The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

The planning authority

The body that approved this project. It has approved 4,607 RERA projects across 33 districts about 1 in 4 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

07

Other projects nearby

The register · within 25 km

92 residential projects still under way within 25 km. Step out ring by ring:

7 projects within 1 km — showing the nearest 6.

SolapurResidential / Group Housing

Godavari Heights

Gayatri Developers

Jun 2025registered
Dec 2026target completion
Government Guidance Rate₹37,454/sq ydScale32 flatsAuthorityMahaRERA
SolapurResidential / Group Housing

Lokmangal oxypark

Lokmangal Properties

Jan 2021registered
Jun 2026target completion
Government Guidance Rate₹37,454/sq ydScale69 flatsAuthorityMahaRERA
SolapurResidential / Group Housing

Jijau Residency

Rachana Developers

Sep 2025registered
Sep 2029target completion
Government Guidance Rate₹37,454/sq ydScale109 flatsAuthorityMahaRERA
SolapurOthers

ROYAL SYNERGY

SHREE JAGDAMB DEVELOPERS

Feb 2025registered
Dec 2029target completion
Government Guidance Rate₹37,454/sq ydScale107 flatsAuthorityMahaRERA
SolapurResidential / Group Housing

Paras Paradise

Anantkoti Developers

Feb 2024registered
Mar 2027target completion
Government Guidance Rate₹37,454/sq ydScale51 flatsAuthorityMahaRERA
SolapurResidential / Group Housing

KHUSHI HERITAGE

KHUSHI BUILDCON

Mar 2024registered
Aug 2026target completion
Government Guidance Rate₹37,454/sq ydScale18 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. This project’s coordinate is approximate, so distances are rough.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.