HORIZON
Share

SAKHA HEIGHTS

P52000028942 · MahaRERA · https://gethorizon.in/projects/sakha-heights-dronagiri-uran-98c765ek

01

Complete project overview

MahaRERA · Registration filing
Units
49 units
Floors
17
Buildings
2
Parking
10 spaces
Land area
1,100 sq m
Sanctioned built-up
1,649 sq m

Timeline

RERA registeredApr 2021
Proposed completionDec 2025
TodaySep 2026
Construction progress
Basement (if any)0%
Podiums0%
Water Supply0%
Landscaping & Tree…0%
Fire protection an…20%
OC-readiness59%
Electrical meter r…60%
Sewerage (Chamber,…70%
Flat fit-out80%
Stilt floor95%
External finishes97%
Excavation100%
Plinth100%
Superstructure100%
Internal finishes100%
Stairs & lifts100%
Water conservation…100%
Open Parking100%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Builder registration

SAKHA LIFESPACE LLP

PartnershipPromoter type
Raigarh, MAHARASHTRABased in
1Projects
1City
2021–2025Active
Timelineevery project, start → promised completion

The only project Horizon has read from this builder so far. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Taluka
Uran
District
Raigarh
Pincode
400702
Survey no.
35
North boundary
15 METER WIDE ROAD
East boundary
PLOT NO 34B
South boundary
PLOT NO 30
West boundary
PLOT NO 35A
What’s nearby
SchoolsNo schools within 2km
HealthcareHospital 2.0km away · 1 clinic within 1km
LifestyleNo parks within 2km
ShoppingNo supermarket within 2km
Getting around
Expressway 3.7 km · Uran Koproli RoadPrimary road 339 m · Panvel Uran RoadRailway line 59 mRailway station 646m away (Dronagiri)Bus stop within 500m
Water & environment
Water body 681 mRiver 815 m
distances only — not a flood assessment
04

Government Guidance Rate

Maharashtra registration department

In Maharashtra it’s called the ready reckoner rate.

No government guidance rate is shown for this project.

Maharashtra's schedule is in Horizon's record, but this project's filed location couldn't be matched to one place with certainty — so no figure is shown rather than a guess.

That is a statement about what Horizon can place — not a sign that no rate exists, and not a signal about the project.

05

Planning authority

MahaRERA · Approved building plan

City and Industrial Development Corporation (CIDCO)

Development Authority
Building Permit
Survey no. 35

The promised possession date (31 Dec 2025) has passed. This record can’t confirm whether the project was completed — that sign-off is the occupancy certificate, below.

The occupancy certificate — the proof that isn’t here

An approved plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the approved plan carries penalty or demolition risk.

The approving body, at scale

City and Industrial Development Corporation (CIDCO)

Metropolitan / development authority

Has approved 885 RERA projectsabout 1 in 23 in Maharashtra.

an apartments market99% apartments · 1% plotted layouts. Apartments like yours are this body's core business.

Builders
724
On record
7,061 flats · 987 plots
Reach
5 districts
Since
2017

Volume and mix are context, not a verdict — a busier body isn’t a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

See every project approved by MahaRERA

07

Other projects nearby

The register · within 25 km

1,948 residential projects still under way within 25 km. Step out ring by ring:

Of the 245 projects the radar draws within 6 km — every kind, every stage — 61 are residential projects still under way. This list keeps only those, and looks further out.

31 projects within 1 km — showing the nearest 6.

180 m awayResidential / Group Housing

Suvidha Villa

Suvidha Enterprises · Dronagiri · Uran

Jun 2026registered
Dec 2032target completion
Scale226 flatsAuthorityMahaRERA
320 m awayOthers

SHREE GANESH RESIDENCY

RAJ HOMES · Bokadvira · Uran

Oct 2023registered
Jun 2028target completion
Government Guidance Rate₹19,315/sq ydScale58 flatsAuthorityMahaRERA
320 m awayOthers

VILLA HERITAGE

KHODAL REALTECH LLP · Uran

Jan 2024registered
Dec 2028target completion
Government Guidance Rate₹30,017/sq ydScale69 flatsAuthorityMahaRERA
320 m awayOthers

VILLA SPRING

KHODAL REALCON LLP · Bokadvira · Uran

Jan 2024registered
Jul 2027target completion
Government Guidance Rate₹19,315/sq ydScale62 flatsAuthorityMahaRERA
320 m awayOthers

VILLA MEADOWS

RITURAJ DEVELOPERS · Bokadvira · Uran

Jul 2024registered
Dec 2027target completion
Government Guidance Rate₹19,315/sq ydScale73 flatsAuthorityMahaRERA
350 m awayOthers

Gami Bianca

LAL GEBI INFRA PRIVATE LIMITED · Dronagiri · Uran

Jun 2023registered
Dec 2027target completion
Scale436 flatsAuthorityMahaRERA

Projects within 25 km, nearest first — closed ones excluded, nothing ranked. Distances from the filed coordinates.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.