Complete project overview

MahaRERA · Registration filing
Floors
8
Buildings
2
Parking
75 spaces
Land area
1,198 sq m
Sanctioned built-up
3,500 sq m

Timeline

RERA registeredNov 2025
Proposed completionDec 2031
TodayJul 2026
Construction progress
Excavation0%
Plinth0%
Stilt floor0%
Superstructure0%
Internal finishes0%
Flat fit-out0%
Stairs & lifts0%
External finishes0%
OC-readiness0%
Water Supply0%
Sewerage (Chamber,…0%
Storm Water Drains0%
Landscaping & Tree…0%
Treatment And Disp…0%
Water conservation…0%
Energy managemcnt0%
Electrical meter r…0%
Per-activity completion % as filed with MahaRERA, shown for in-progress projects — a snapshot, not a live tracker.
02

Builder’s track record

MahaRERA · Promoter registration

SHREE SAI BUILDCON

PartnershipPromoter type
Satara, MAHARASHTRABased in
5Projects
4Cities
2021–presentActive
Timelineevery project, start → promised completion
Builder DNAthe whole portfolio, summed
26 homeson the public record across 5 projects
16,827 sq mbuilt-up filed
4,479 sq mland declared

These are sums of what the promoter has put on the public record across their projects — a sense of how big a builder this is, not build quality and not whether they finish on time.

Planning authoritiesthis builder's portfolio, by approving body
Ahmedabad Urban Development AuthorityUrban Development Authority1 of 4 projects
Nashik Municipal CorporationMunicipal Corporation1 of 4 projects
Pimpri Chinchwad Municipal CorporationMunicipal Corporation1 of 4 projects
Satara Municipal Corporation SataraMunicipal Corporationthis project1 of 4 projects

Counts are how many of this builder’s projects on Horizon’s record were approved by each body — a footprint, not a ranking of the authorities.

Every project Horizon has read from this promoter, oldest first on the timeline. Dates are the project’s start (where filed) and target-completion dates on the RERA filing; delivery isn’t reported here.

03

Location

MahaRERA · Registration filing
Village
Godoli (CT)
Taluka
Satara
District
Satara
Pincode
415002
Survey no.
S.NO.27/2/1 Plot No 14
North boundary
12 Mtrs. Width Road
East boundary
Adjoining Survey No. 29
South boundary
Adjoining Survey No. 29
West boundary
Survey No. 27/ 2/ 1 / Plot No. 15
What’s nearby
SchoolsNo schools within 2km · 3 educational institutions within 1km · College or university 596m away
HealthcareHospital 188m away · 1 clinic within 1km
LifestylePark 1.0km away
ShoppingNo supermarket within 2km
Getting around
Expressway 444 mPrimary road 213 m · Satara-Bangalore HighwayRailway line 4.6 km · Pune - Miraj Railway LineRailway station 4.8km away (Satara)Limited bus connectivity nearby
Water & environment
Canal 1.6 kmWater body 2.1 km
distances only — not a flood assessment
04

Planning authority

MahaRERA · Approved building plan

Satara Municipal Corporation Satara

Municipal Corporation
Building Permit
Survey no. S.NO.27/2/1 Plot No 14
The occupancy certificate — the proof that isn’t here

A sanctioned plan is the government’s approval to build. It is not proof the project was built to that plan. That sign-off is the Occupancy Certificate (OC) — issued by the planning authority, the same body that approved the plan, not by RERA— and it isn’t in this record. Ask the builder for it, or check with the authority. Without an OC, banks may decline home loans, and any deviation from the sanctioned plan carries penalty or demolition risk.

The approving body, at scale

Municipal Corporation

A city municipal corporation that sanctions projects within its own limits. It has approved 12,653 RERA projects across 34 districts about 1 in 2 in Maharashtra.

Volume is context, not a verdict — a busier authority is not a safer project. And this counts RERA-registered projects on Horizon’s record, not all construction.

Legal & regulatory record
LitigationNone declared to MahaRERA
From MahaRERA's record — the litigation flag is the promoter's declaration; complaints, appeals and non-compliance notices are the authority's own filings. A flagged line is worth checking with the authority; none of it is a verdict on the project.
Complaints register

None on record with MahaRERA against this project.

Only disputes escalated to the authority appear on the register — a private disagreement never filed here would not. A count from the public record, not a verdict.

What this record cannot tell you

  • Build quality — no filing records how well it was actually built.
  • Private disputes — only complaints escalated to the authority appear here.
  • What it will be worth — the record is the past; it does not price the future.